Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa)
Physical Progress
64.0%
Drone-monitored
Financial Progress
62.3%
Of awarded cost
Awarded Cost
₹137 Cr
Contract value
Length
2.75 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
246
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
30-01-2024
Likely Date
28-02-2027
Completion
64.0%
Physical Done
Project Timeline
Awarded
30-07-2022
Construction Started
30-07-2022
In Progress
Near Completion
-
Completed
28-02-2027
Physical vs Financial Progress
Project Details
UPC
N/02022/02003/BR
National Highway
27
Regional Office
RO-Patna
State
Bihar
Mode
Item Rate
Length
2.75 km
Contractor
Ganesh Ram Dokania
Project Stage
Under Construction (AD issued)
Drone Frames
246 frames
Last Flight
2026-03-27
Cost & Timeline
Awarded Cost
₹137.23 Cr
Capital Cost
₹210.05 Cr
Start Date
30-07-2022
PCOD Date
-
Scheduled Completion
30-01-2024
Likely Completion
28-02-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 09:20:16
Contractor Profile
Ganesh Ram Dokania
Project Intelligence
Project is more than halfway complete at 64.0% physical progress.
Project is on schedule or ahead of planned completion date.
Covers 2.75 km on 27, improving regional connectivity.
246 drone frames uploaded — real-time aerial monitoring is active for this project.
Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa) is a National Highways Authority of India (NHAI) project on 27 in Bihar. The project has an awarded cost of ₹137.23 Cr and is currently ongoing with physical progress at 64.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
246 frames · NHAI surveillance footage · UPC N/02022/02003/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa)"?
- Current physical progress: 64.0%. Financial progress: 62.3%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 30-01-2024. Likely completion: 28-02-2027.
- Who is the contractor for this NHAI highway project?
- The contractor for Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa) is Ganesh Ram Dokania. The project is under RO-Patna and covers 2.75 km on 27.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹137.23 Crore. Total capital cost: ₹210.05 Crore. The project is on 27 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/02022/02003/BR in NHAI?
- UPC (Unique Project Code) N/02022/02003/BR refers to "Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa)" — a National Highway project on 27 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.