Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
All NHAI Projects
27Item Rate 246 Drone Frames

Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa)

UPC: N/02022/02003/BR

Physical Progress

64.0%

Drone-monitored

Financial Progress

62.3%

Of awarded cost

Awarded Cost

₹137 Cr

Contract value

Length

2.75 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

246

Aerial captures

Project Progress

Physical Progress64.0%
Financial Progress62.3%

Stage

Under Construction (AD issued)

Due Date

30-01-2024

Likely Date

28-02-2027

Completion

64.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

30-07-2022

Construction Started

30-07-2022

In Progress

Near Completion

-

Completed

28-02-2027

Physical vs Financial Progress

Project Details

UPC

N/02022/02003/BR

National Highway

27

Regional Office

RO-Patna

State

Bihar

Mode

Item Rate

Length

2.75 km

Contractor

Ganesh Ram Dokania

Project Stage

Under Construction (AD issued)

Drone Frames

246 frames

Last Flight

2026-03-27

Cost & Timeline

Awarded Cost

₹137.23 Cr

Capital Cost

₹210.05 Cr

Start Date

30-07-2022

PCOD Date

-

Scheduled Completion

30-01-2024

Likely Completion

28-02-2027

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-06-16 09:20:16

Contractor Profile

Ganesh Ram Dokania

RO-Patna27Item Rate

Project Intelligence

1

Project is more than halfway complete at 64.0% physical progress.

2

Project is on schedule or ahead of planned completion date.

3

Covers 2.75 km on 27, improving regional connectivity.

4

246 drone frames uploaded — real-time aerial monitoring is active for this project.

Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa) is a National Highways Authority of India (NHAI) project on 27 in Bihar. The project has an awarded cost of ₹137.23 Cr and is currently ongoing with physical progress at 64.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

246 frames · NHAI surveillance footage · UPC N/02022/02003/BR

View Drone Images

Frequently Asked Questions

What is the current status of the NHAI project "Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa)"?
Current physical progress: 64.0%. Financial progress: 62.3%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 30-01-2024. Likely completion: 28-02-2027.
Who is the contractor for this NHAI highway project?
The contractor for Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa) is Ganesh Ram Dokania. The project is under RO-Patna and covers 2.75 km on 27.
What is the cost of this NHAI highway project?
The awarded cost is ₹137.23 Crore. Total capital cost: ₹210.05 Crore. The project is on 27 in Bihar, monitored via drone surveillance by NHAI.
What is UPC N/02022/02003/BR in NHAI?
UPC (Unique Project Code) N/02022/02003/BR refers to "Balance work - WB-10 (Gandak Bridge) Km 402.00 to Km 440.00 (Devanpur - Kotwa)" — a National Highway project on 27 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.