Maheshkunt-Saharsa-Purnea (Pkg I) km 0.00 to km. 90.00 of NH-107
Physical Progress
88.4%
Drone-monitored
Financial Progress
84.1%
Of awarded cost
Awarded Cost
₹645 Cr
Contract value
Length
90 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
7963
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
19-12-2021
Likely Date
30-09-2026
Completion
88.4%
Physical Done
Project Timeline
Awarded
20-12-2019
Construction Started
20-12-2019
In Progress
Near Completion
-
Completed
30-09-2026
Physical vs Financial Progress
Project Details
UPC
N/08052/01001/BR
National Highway
231
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
90 km
Contractor
Gannon Dunkerley and Co. Ltd
Project Stage
Under Construction (AD issued)
Drone Frames
7963 frames
Last Flight
2026-05-27
Cost & Timeline
Awarded Cost
₹644.50 Cr
Capital Cost
₹662.44 Cr
Start Date
20-12-2019
PCOD Date
-
Scheduled Completion
19-12-2021
Likely Completion
30-09-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 09:07:57
Contractor Profile
Gannon Dunkerley and Co. Ltd
Project Intelligence
Construction is 88.4% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 90 km on 231, improving regional connectivity.
7963 drone frames uploaded — real-time aerial monitoring is active for this project.
Maheshkunt-Saharsa-Purnea (Pkg I) km 0.00 to km. 90.00 of NH-107 is a National Highways Authority of India (NHAI) project on 231 in Bihar. The project has an awarded cost of ₹644.50 Cr and is currently ongoing with physical progress at 88.4%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
7,963 frames · NHAI surveillance footage · UPC N/08052/01001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Maheshkunt-Saharsa-Purnea (Pkg I) km 0.00 to km. 90.00 of NH-107"?
- Current physical progress: 88.4%. Financial progress: 84.1%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 19-12-2021. Likely completion: 30-09-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for Maheshkunt-Saharsa-Purnea (Pkg I) km 0.00 to km. 90.00 of NH-107 is Gannon Dunkerley and Co. Ltd. The project is under RO-Patna and covers 90 km on 231.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹644.50 Crore. Total capital cost: ₹662.44 Crore. The project is on 231 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/08052/01001/BR in NHAI?
- UPC (Unique Project Code) N/08052/01001/BR refers to "Maheshkunt-Saharsa-Purnea (Pkg I) km 0.00 to km. 90.00 of NH-107" — a National Highway project on 231 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.