Maheshkunt -Saharsa-Purnea Pkg II
Physical Progress
91.0%
Drone-monitored
Financial Progress
79.5%
Of awarded cost
Awarded Cost
₹736 Cr
Contract value
Length
87.96 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
8718
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
11-12-2020
Likely Date
30-09-2026
Completion
91.0%
Physical Done
Project Timeline
Awarded
13-12-2018
Construction Started
13-12-2018
In Progress
Near Completion
-
Completed
30-09-2026
Physical vs Financial Progress
Project Details
UPC
N/08052/02001/BR
National Highway
231
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
87.96 km
Contractor
Gammon Engineers & Contractors Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
8718 frames
Last Flight
2026-02-23
Cost & Timeline
Awarded Cost
₹736.01 Cr
Capital Cost
₹1245.33 Cr
Start Date
13-12-2018
PCOD Date
-
Scheduled Completion
11-12-2020
Likely Completion
30-09-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 12:52:39
Contractor Profile
Gammon Engineers & Contractors Pvt. Ltd.
Project Intelligence
Construction is 91.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 87.96 km on 231, improving regional connectivity.
8718 drone frames uploaded — real-time aerial monitoring is active for this project.
Maheshkunt -Saharsa-Purnea Pkg II is a National Highways Authority of India (NHAI) project on 231 in Bihar. The project has an awarded cost of ₹736.01 Cr and is currently ongoing with physical progress at 91.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
8,718 frames · NHAI surveillance footage · UPC N/08052/02001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Maheshkunt -Saharsa-Purnea Pkg II"?
- Current physical progress: 91.0%. Financial progress: 79.5%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 11-12-2020. Likely completion: 30-09-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for Maheshkunt -Saharsa-Purnea Pkg II is Gammon Engineers & Contractors Pvt. Ltd.. The project is under RO-Patna and covers 87.96 km on 231.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹736.01 Crore. Total capital cost: ₹1245.33 Crore. The project is on 231 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/08052/02001/BR in NHAI?
- UPC (Unique Project Code) N/08052/02001/BR refers to "Maheshkunt -Saharsa-Purnea Pkg II" — a National Highway project on 231 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.