Construction of four laning of Bakarpur- Manikpur road section starting from village Chitarsenpur (km 0+000) and terminating at SH-74 near Manikpur (38+814) at NH-139W under Bharatmalapariyona

UPC: N/06044/01001/BR

Physical Progress

48.8%

Drone-monitored

Financial Progress

50.1%

Of awarded cost

Awarded Cost

₹1122 Cr

Contract value

Length

38.81 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

3704

Aerial captures

Project Progress

Physical Progress48.8%
Financial Progress50.1%

Stage

Under Construction (AD issued)

Due Date

05-04-2027

Likely Date

30-09-2027

Completion

48.8%

Physical Done

DoneRemaining

Project Timeline

Awarded

08-10-2024

Construction Started

08-10-2024

In Progress

Near Completion

-

Completed

30-09-2027

Physical vs Financial Progress

Project Details

UPC

N/06044/01001/BR

National Highway

139W

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

38.81 km

Contractor

RKD Construction Pvt. Ltd.

Project Stage

Under Construction (AD issued)

Drone Frames

3704 frames

Last Flight

2026-08-27

Cost & Timeline

Awarded Cost

₹1121.65 Cr

Capital Cost

₹1422.37 Cr

Start Date

08-10-2024

PCOD Date

-

Scheduled Completion

05-04-2027

Likely Completion

30-09-2027

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-13 14:09:49

Contractor Profile

RKD Construction Pvt. Ltd.

RO-Patna139WHAM

Project Intelligence

1

Physical progress stands at 48.8%. Financial utilization at 50.1%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 38.81 km on 139W, improving regional connectivity.

4

3704 drone frames uploaded — real-time aerial monitoring is active for this project.

Construction of four laning of Bakarpur- Manikpur road section starting from village Chitarsenpur (km 0+000) and terminating at SH-74 near Manikpur (38+814) at NH-139W under Bharatmalapariyona is a National Highways Authority of India (NHAI) project on 139W in Bihar. The project has an awarded cost of ₹1121.65 Cr and is currently ongoing with physical progress at 48.8%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

3,704 frames · NHAI surveillance footage · UPC N/06044/01001/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "Construction of four laning of Bakarpur- Manikpur road section starting from vil"?
Current physical progress: 48.8%. Financial progress: 50.1%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 05-04-2027. Likely completion: 30-09-2027.
QWho is the contractor for this NHAI highway project?
The contractor for Construction of four laning of Bakarpur- Manikpur road section starting from village Chitarsenpur (km 0+000) and terminating at SH-74 near Manikpur (38+814) at NH-139W under Bharatmalapariyona is RKD Construction Pvt. Ltd.. The project is under RO-Patna and covers 38.81 km on 139W.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹1121.65 Crore. Total capital cost: ₹1422.37 Crore. The project is on 139W in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/06044/01001/BR in NHAI?
UPC (Unique Project Code) N/06044/01001/BR refers to "Construction of four laning of Bakarpur- Manikpur road section starting from village Chitarsenpur (km 0+000) and terminating at SH-74 near Manikpur (38+814) at NH-139W under Bharatmalapariyona" — a National Highway project on 139W in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.