Construction of four laning of Bakarpur- Manikpur road section starting from village Chitarsenpur (km 0+000) and terminating at SH-74 near Manikpur (38+814) at NH-139W under Bharatmalapariyona
Physical Progress
48.8%
Drone-monitored
Financial Progress
50.1%
Of awarded cost
Awarded Cost
₹1122 Cr
Contract value
Length
38.81 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
3704
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
05-04-2027
Likely Date
30-09-2027
Completion
48.8%
Physical Done
Project Timeline
Awarded
08-10-2024
Construction Started
08-10-2024
In Progress
Near Completion
-
Completed
30-09-2027
Physical vs Financial Progress
Project Details
UPC
N/06044/01001/BR
National Highway
139W
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
38.81 km
Contractor
RKD Construction Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
3704 frames
Last Flight
2026-08-27
Cost & Timeline
Awarded Cost
₹1121.65 Cr
Capital Cost
₹1422.37 Cr
Start Date
08-10-2024
PCOD Date
-
Scheduled Completion
05-04-2027
Likely Completion
30-09-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-13 14:09:49
Contractor Profile
RKD Construction Pvt. Ltd.
Project Intelligence
Physical progress stands at 48.8%. Financial utilization at 50.1%.
Project is on schedule or ahead of planned completion date.
Covers 38.81 km on 139W, improving regional connectivity.
3704 drone frames uploaded — real-time aerial monitoring is active for this project.
Construction of four laning of Bakarpur- Manikpur road section starting from village Chitarsenpur (km 0+000) and terminating at SH-74 near Manikpur (38+814) at NH-139W under Bharatmalapariyona is a National Highways Authority of India (NHAI) project on 139W in Bihar. The project has an awarded cost of ₹1121.65 Cr and is currently ongoing with physical progress at 48.8%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
3,704 frames · NHAI surveillance footage · UPC N/06044/01001/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Construction of four laning of Bakarpur- Manikpur road section starting from vil"?
- Current physical progress: 48.8%. Financial progress: 50.1%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 05-04-2027. Likely completion: 30-09-2027.
- QWho is the contractor for this NHAI highway project?
- The contractor for Construction of four laning of Bakarpur- Manikpur road section starting from village Chitarsenpur (km 0+000) and terminating at SH-74 near Manikpur (38+814) at NH-139W under Bharatmalapariyona is RKD Construction Pvt. Ltd.. The project is under RO-Patna and covers 38.81 km on 139W.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹1121.65 Crore. Total capital cost: ₹1422.37 Crore. The project is on 139W in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/06044/01001/BR in NHAI?
- UPC (Unique Project Code) N/06044/01001/BR refers to "Construction of four laning of Bakarpur- Manikpur road section starting from village Chitarsenpur (km 0+000) and terminating at SH-74 near Manikpur (38+814) at NH-139W under Bharatmalapariyona" — a National Highway project on 139W in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.