Physical Progress
42.3%
Drone-monitored
Financial Progress
40.1%
Of awarded cost
Awarded Cost
₹1122 Cr
Contract value
Length
38.81 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
3628
Aerial captures
Stage
Under Construction (AD issued)
Due Date
05-04-2027
Likely Date
30-09-2027
42.3%
Physical Done
Awarded
08-10-2024
Construction Started
08-10-2024
In Progress
Near Completion
-
Completed
30-09-2027
UPC
N/06044/01001/BR
National Highway
139W
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
38.81 km
Contractor
RKD Construction Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
3628 frames
Last Flight
2026-03-24
Awarded Cost
₹1121.65 Cr
Capital Cost
₹1422.37 Cr
Start Date
08-10-2024
PCOD Date
-
Scheduled Completion
05-04-2027
Likely Completion
30-09-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 12:47:17
RKD Construction Pvt. Ltd.
Physical progress stands at 42.3%. Financial utilization at 40.1%.
Project is on schedule or ahead of planned completion date.
Covers 38.81 km on 139W, improving regional connectivity.
3628 drone frames uploaded — real-time aerial monitoring is active for this project.
3,628 frames · NHAI surveillance footage · UPC N/06044/01001/BR