4L PS under NH configuration of Manikpur-Sahebganj of NH-139W
Physical Progress
21.5%
Drone-monitored
Financial Progress
10.0%
Of awarded cost
Awarded Cost
₹984 Cr
Contract value
Length
44.65 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4552
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
31-12-2027
Likely Date
31-12-2027
Completion
21.5%
Physical Done
Project Timeline
Awarded
01-01-2026
Construction Started
01-01-2026
In Progress
Near Completion
-
Completed
31-12-2027
Physical vs Financial Progress
Project Details
UPC
N/06044/02001/BR
National Highway
139W
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
44.65 km
Contractor
JSP Project Pvt Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
4552 frames
Last Flight
2026-01-27
Cost & Timeline
Awarded Cost
₹984.20 Cr
Capital Cost
₹1538.76 Cr
Start Date
01-01-2026
PCOD Date
-
Scheduled Completion
31-12-2027
Likely Completion
31-12-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 13:00:05
Contractor Profile
JSP Project Pvt Ltd.
Project Intelligence
Physical progress stands at 21.5%. Financial utilization at 10.0%.
Project is on schedule or ahead of planned completion date.
Covers 44.65 km on 139W, improving regional connectivity.
4552 drone frames uploaded — real-time aerial monitoring is active for this project.
4L PS under NH configuration of Manikpur-Sahebganj of NH-139W is a National Highways Authority of India (NHAI) project on 139W in Bihar. The project has an awarded cost of ₹984.20 Cr and is currently ongoing with physical progress at 21.5%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
4,552 frames · NHAI surveillance footage · UPC N/06044/02001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L PS under NH configuration of Manikpur-Sahebganj of NH-139W"?
- Current physical progress: 21.5%. Financial progress: 10.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 31-12-2027. Likely completion: 31-12-2027.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L PS under NH configuration of Manikpur-Sahebganj of NH-139W is JSP Project Pvt Ltd.. The project is under RO-Patna and covers 44.65 km on 139W.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹984.20 Crore. Total capital cost: ₹1538.76 Crore. The project is on 139W in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/06044/02001/BR in NHAI?
- UPC (Unique Project Code) N/06044/02001/BR refers to "4L PS under NH configuration of Manikpur-Sahebganj of NH-139W" — a National Highway project on 139W in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.