Physical Progress
21.5%
Drone-monitored
Financial Progress
10.0%
Of awarded cost
Awarded Cost
₹984 Cr
Contract value
Length
44.65 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4552
Aerial captures
Stage
Under Construction (AD issued)
Due Date
31-12-2027
Likely Date
31-12-2027
21.5%
Physical Done
Awarded
01-01-2026
Construction Started
01-01-2026
In Progress
Near Completion
-
Completed
31-12-2027
UPC
N/06044/02001/BR
National Highway
139W
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
44.65 km
Contractor
JSP Project Pvt Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
4552 frames
Last Flight
2026-01-27
Awarded Cost
₹984.20 Cr
Capital Cost
₹1538.76 Cr
Start Date
01-01-2026
PCOD Date
-
Scheduled Completion
31-12-2027
Likely Completion
31-12-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 13:00:05
JSP Project Pvt Ltd.
Physical progress stands at 21.5%. Financial utilization at 10.0%.
Project is on schedule or ahead of planned completion date.
Covers 44.65 km on 139W, improving regional connectivity.
4552 drone frames uploaded — real-time aerial monitoring is active for this project.
4,552 frames · NHAI surveillance footage · UPC N/06044/02001/BR