Physical Progress
100.0%
Drone-monitored
Financial Progress
99.5%
Of awarded cost
Awarded Cost
₹427 Cr
Contract value
Length
73.07 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
8338
Aerial captures
Stage
CC Issued
Due Date
05-04-2018
Likely Date
30-04-2021
100.0%
Physical Done
Awarded
05-04-2016
Construction Started
05-04-2016
In Progress
Near Completion
31-01-2018
Completed
30-04-2021
UPC
N/08034/01001/BR
National Highway
722
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
73.07 km
Contractor
R. K. Jain Infra Projects Pvt. Ltd.
Project Stage
CC Issued
Drone Frames
8338 frames
Last Flight
2025-06-26
Awarded Cost
₹427.06 Cr
Capital Cost
₹649.27 Cr
Start Date
05-04-2016
PCOD Date
31-01-2018
Scheduled Completion
05-04-2018
Likely Completion
30-04-2021
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-19 16:42:37
R. K. Jain Infra Projects Pvt. Ltd.
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 73.07 km on 722, improving regional connectivity.
8338 drone frames uploaded — real-time aerial monitoring is active for this project.
8,338 frames · NHAI surveillance footage · UPC N/08034/01001/BR