Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630
Physical Progress
97.8%
Drone-monitored
Financial Progress
51.2%
Of awarded cost
Awarded Cost
₹1065 Cr
Contract value
Length
47.22 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4807
Aerial captures
Project Progress
Stage
PCC Issued, CC Pending
Due Date
11-07-2023
Likely Date
31-07-2026
Completion
97.8%
Physical Done
Project Timeline
Awarded
28-04-2021
Construction Started
28-04-2021
In Progress
Near Completion
27-04-2023
Completed
31-07-2026
Physical vs Financial Progress
Project Details
UPC
N/08025/01003/BR
National Highway
20
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
47.22 km
Contractor
Gawar Construction Ltd
Project Stage
PCC Issued, CC Pending
Drone Frames
4807 frames
Last Flight
2025-03-25
Cost & Timeline
Awarded Cost
₹1065.00 Cr
Capital Cost
₹897.45 Cr
Start Date
28-04-2021
PCOD Date
27-04-2023
Scheduled Completion
11-07-2023
Likely Completion
31-07-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 17:56:02
Contractor Profile
Gawar Construction Ltd
Project Intelligence
Construction is 97.8% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 47.22 km on 20, improving regional connectivity.
4807 drone frames uploaded — real-time aerial monitoring is active for this project.
Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630 is a National Highways Authority of India (NHAI) project on 20 in Bihar. The project has an awarded cost of ₹1065.00 Cr and is currently **ongoing** with physical progress at 97.8%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
4,807 frames · NHAI surveillance footage · UPC N/08025/01003/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630"?
- Current physical progress: 97.8%. Financial progress: 51.2%. Project stage: PCC Issued, CC Pending. On schedule. Scheduled completion: 11-07-2023. Likely completion: 31-07-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630 is Gawar Construction Ltd. The project is under RO-Patna and covers 47.22 km on 20.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1065.00 Crore. Total capital cost: ₹897.45 Crore. The project is on 20 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/08025/01003/BR in NHAI?
- UPC (Unique Project Code) N/08025/01003/BR refers to "Bakhtiyarpur-Rajauli Pkg-II from km. 54.405 to km.101.630" — a National Highway project on 20 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.