Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520
Physical Progress
99.1%
Drone-monitored
Financial Progress
40.0%
Of awarded cost
Awarded Cost
₹2310 Cr
Contract value
Length
50.89 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4188
Aerial captures
Project Progress
Stage
PCC Issued, CC Pending
Due Date
27-06-2024
Likely Date
30-09-2026
Completion
99.1%
Physical Done
Project Timeline
Awarded
31-12-2021
Construction Started
31-12-2021
In Progress
Near Completion
20-01-2025
Completed
30-09-2026
Physical vs Financial Progress
Project Details
UPC
N/08025/01004/BR
National Highway
20
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
50.89 km
Contractor
Gawar Construction Ltd
Project Stage
PCC Issued, CC Pending
Drone Frames
4188 frames
Last Flight
2026-06-27
Cost & Timeline
Awarded Cost
₹2310.00 Cr
Capital Cost
₹2156.22 Cr
Start Date
31-12-2021
PCOD Date
20-01-2025
Scheduled Completion
27-06-2024
Likely Completion
30-09-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-20 21:21:04
Contractor Profile
Gawar Construction Ltd
Project Intelligence
This is a mega infrastructure project worth ₹2310 Cr — among the largest NHAI projects in the region.
Construction is 99.1% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 50.89 km on 20, improving regional connectivity.
4188 drone frames uploaded — real-time aerial monitoring is active for this project.
Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520 is a National Highways Authority of India (NHAI) project on 20 in Bihar. The project has an awarded cost of ₹2310.00 Cr and is currently ongoing with physical progress at 99.1%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
4,188 frames · NHAI surveillance footage · UPC N/08025/01004/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520"?
- Current physical progress: 99.1%. Financial progress: 40.0%. Project stage: PCC Issued, CC Pending. On schedule. Scheduled completion: 27-06-2024. Likely completion: 30-09-2026.
- QWho is the contractor for this NHAI highway project?
- The contractor for Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520 is Gawar Construction Ltd. The project is under RO-Patna and covers 50.89 km on 20.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹2310.00 Crore. Total capital cost: ₹2156.22 Crore. The project is on 20 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/08025/01004/BR in NHAI?
- UPC (Unique Project Code) N/08025/01004/BR refers to "Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520" — a National Highway project on 20 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.