Construction of Approach Road to Rail-cum- Road Bridge across river Ganga at Munger Ghat ( NH-333 B)
Physical Progress
100.0%
Drone-monitored
Financial Progress
100.0%
Of awarded cost
Awarded Cost
₹239 Cr
Contract value
Length
14.52 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
1469
Aerial captures
Project Progress
Stage
PCC Issued, CC Pending
Due Date
28-05-2021
Likely Date
30-06-2026
Completion
100.0%
Physical Done
Project Timeline
Awarded
01-12-2018
Construction Started
01-12-2018
In Progress
Near Completion
30-09-2022
Completed
30-06-2026
Physical vs Financial Progress
Project Details
UPC
N/09077/01001/BR
National Highway
333B
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
14.52 km
Contractor
S.P. Singla Construction Pvt. Ltd
Project Stage
PCC Issued, CC Pending
Drone Frames
1469 frames
Last Flight
2025-02-25
Cost & Timeline
Awarded Cost
₹239.16 Cr
Capital Cost
₹537.88 Cr
Start Date
01-12-2018
PCOD Date
30-09-2022
Scheduled Completion
28-05-2021
Likely Completion
30-06-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 20:28:48
Contractor Profile
S.P. Singla Construction Pvt. Ltd
Project Intelligence
Construction is 100.0% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 14.52 km on 333B, improving regional connectivity.
1469 drone frames uploaded — real-time aerial monitoring is active for this project.
Construction of Approach Road to Rail-cum- Road Bridge across river Ganga at Munger Ghat ( NH-333 B) is a National Highways Authority of India (NHAI) project on 333B in Bihar. The project has an awarded cost of ₹239.16 Cr and is currently **ongoing** with physical progress at 100.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
1,469 frames · NHAI surveillance footage · UPC N/09077/01001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Construction of Approach Road to Rail-cum- Road Bridge across river Ganga at Mun"?
- Current physical progress: 100.0%. Financial progress: 100.0%. Project stage: PCC Issued, CC Pending. On schedule. Scheduled completion: 28-05-2021. Likely completion: 30-06-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for Construction of Approach Road to Rail-cum- Road Bridge across river Ganga at Munger Ghat ( NH-333 B) is S.P. Singla Construction Pvt. Ltd. The project is under RO-Patna and covers 14.52 km on 333B.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹239.16 Crore. Total capital cost: ₹537.88 Crore. The project is on 333B in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/09077/01001/BR in NHAI?
- UPC (Unique Project Code) N/09077/01001/BR refers to "Construction of Approach Road to Rail-cum- Road Bridge across river Ganga at Munger Ghat ( NH-333 B)" — a National Highway project on 333B in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.