Repair of service road, Construction of RE wall; slope protection work Earth filling work (Weight bridge) and Safety work for Approaches to Rail - cum -Road Bridge across River Ganga at Munger Ghat near Munger of NH-333B in state of Bihar
Physical Progress
0.0%
Drone-monitored
Financial Progress
0.0%
Of awarded cost
Awarded Cost
₹1 Cr
Contract value
Length
14.517 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
N/A
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
10-06-2026
Likely Date
30-09-2026
Completion
0.0%
Physical Done
Project Timeline
Awarded
05-03-2026
Construction Started
05-03-2026
In Progress
Near Completion
-
Completed
30-09-2026
Physical vs Financial Progress
Project Details
UPC
N/08038/01007/BR
National Highway
333B
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
14.517 km
Contractor
Descon Infrastructure Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
N/A
Last Flight
N/A
Cost & Timeline
Awarded Cost
₹1.32 Cr
Capital Cost
N/A
Start Date
05-03-2026
PCOD Date
-
Scheduled Completion
10-06-2026
Likely Completion
30-09-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-20 21:44:22
Contractor Profile
Descon Infrastructure Pvt. Ltd.
Project Intelligence
Physical progress stands at 0.0%. Financial utilization at 0.0%.
Project is on schedule or ahead of planned completion date.
Covers 14.517 km on 333B, improving regional connectivity.
Repair of service road, Construction of RE wall; slope protection work Earth filling work (Weight bridge) and Safety work for Approaches to Rail - cum -Road Bridge across River Ganga at Munger Ghat near Munger of NH-333B in state of Bihar is a National Highways Authority of India (NHAI) project on 333B in Bihar. The project has an awarded cost of ₹1.32 Cr and is currently ongoing with physical progress at 0.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Repair of service road, Construction of RE wall; slope protection work Earth fil"?
- Current physical progress: 0.0%. Financial progress: 0.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 10-06-2026. Likely completion: 30-09-2026.
- QWho is the contractor for this NHAI highway project?
- The contractor for Repair of service road, Construction of RE wall; slope protection work Earth filling work (Weight bridge) and Safety work for Approaches to Rail - cum -Road Bridge across River Ganga at Munger Ghat near Munger of NH-333B in state of Bihar is Descon Infrastructure Pvt. Ltd.. The project is under RO-Patna and covers 14.517 km on 333B.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹1.32 Crore. The project is on 333B in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/08038/01007/BR in NHAI?
- UPC (Unique Project Code) N/08038/01007/BR refers to "Repair of service road, Construction of RE wall; slope protection work Earth filling work (Weight bridge) and Safety work for Approaches to Rail - cum -Road Bridge across River Ganga at Munger Ghat near Munger of NH-333B in state of Bihar " — a National Highway project on 333B in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.