4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3)
Physical Progress
72.2%
Drone-monitored
Financial Progress
32.0%
Of awarded cost
Awarded Cost
₹1017 Cr
Contract value
Length
32.35 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2628
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
12-04-2024
Likely Date
31-12-2026
Completion
72.2%
Physical Done
Project Timeline
Awarded
06-04-2022
Construction Started
06-04-2022
In Progress
Near Completion
-
Completed
31-12-2026
Physical vs Financial Progress
Project Details
UPC
N/08038/03003/BR
National Highway
80
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
32.35 km
Contractor
Montecarlo Munger Mirzachauki 3 highway Private Limited
Project Stage
Under Construction (AD issued)
Drone Frames
2628 frames
Last Flight
2026-02-24
Cost & Timeline
Awarded Cost
₹1017.00 Cr
Capital Cost
₹1769.50 Cr
Start Date
06-04-2022
PCOD Date
-
Scheduled Completion
12-04-2024
Likely Completion
31-12-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 11:25:29
Contractor Profile
Montecarlo Munger Mirzachauki 3 highway Private Limited
Project Intelligence
Project is more than halfway complete at 72.2% physical progress.
Project is on schedule or ahead of planned completion date.
Covers 32.35 km on 80, improving regional connectivity.
2628 drone frames uploaded — real-time aerial monitoring is active for this project.
4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3) is a National Highways Authority of India (NHAI) project on 80 in Bihar. The project has an awarded cost of ₹1017.00 Cr and is currently ongoing with physical progress at 72.2%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
2,628 frames · NHAI surveillance footage · UPC N/08038/03003/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Ra"?
- Current physical progress: 72.2%. Financial progress: 32.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 12-04-2024. Likely completion: 31-12-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3) is Montecarlo Munger Mirzachauki 3 highway Private Limited. The project is under RO-Patna and covers 32.35 km on 80.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1017.00 Crore. Total capital cost: ₹1769.50 Crore. The project is on 80 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/08038/03003/BR in NHAI?
- UPC (Unique Project Code) N/08038/03003/BR refers to "4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3)" — a National Highway project on 80 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.