4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3)

UPC: N/08038/03003/BR

Physical Progress

81.0%

Drone-monitored

Financial Progress

78.5%

Of awarded cost

Awarded Cost

₹1017 Cr

Contract value

Length

32.35 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

2829

Aerial captures

Project Progress

Physical Progress81.0%
Financial Progress78.5%

Stage

Under Construction (AD issued)

Due Date

12-04-2024

Likely Date

31-12-2026

Completion

81.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

06-04-2022

Construction Started

06-04-2022

In Progress

Near Completion

-

Completed

31-12-2026

Physical vs Financial Progress

Project Details

UPC

N/08038/03003/BR

National Highway

80

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

32.35 km

Contractor

Montecarlo Munger Mirzachauki 3 highway Private Limited

Project Stage

Under Construction (AD issued)

Drone Frames

2829 frames

Last Flight

2026-07-27

Cost & Timeline

Awarded Cost

₹1017.00 Cr

Capital Cost

₹1769.50 Cr

Start Date

06-04-2022

PCOD Date

-

Scheduled Completion

12-04-2024

Likely Completion

31-12-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-08-29 09:46:51

Contractor Profile

Montecarlo Munger Mirzachauki 3 highway Private Limited

RO-Patna80HAM

Project Intelligence

1

Construction is 81.0% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 32.35 km on 80, improving regional connectivity.

4

2829 drone frames uploaded — real-time aerial monitoring is active for this project.

4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3) is a National Highways Authority of India (NHAI) project on 80 in Bihar. The project has an awarded cost of ₹1017.00 Cr and is currently ongoing with physical progress at 81.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

2,829 frames · NHAI surveillance footage · UPC N/08038/03003/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Ra"?
Current physical progress: 81.0%. Financial progress: 78.5%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 12-04-2024. Likely completion: 31-12-2026.
QWho is the contractor for this NHAI highway project?
The contractor for 4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3) is Montecarlo Munger Mirzachauki 3 highway Private Limited. The project is under RO-Patna and covers 32.35 km on 80.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹1017.00 Crore. Total capital cost: ₹1769.50 Crore. The project is on 80 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/08038/03003/BR in NHAI?
UPC (Unique Project Code) N/08038/03003/BR refers to "4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3)" — a National Highway project on 80 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.