Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
All NHAI Projects
80HAM 2628 Drone Frames

4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3)

UPC: N/08038/03003/BR

Physical Progress

72.2%

Drone-monitored

Financial Progress

32.0%

Of awarded cost

Awarded Cost

₹1017 Cr

Contract value

Length

32.35 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

2628

Aerial captures

Project Progress

Physical Progress72.2%
Financial Progress32.0%

Stage

Under Construction (AD issued)

Due Date

12-04-2024

Likely Date

31-12-2026

Completion

72.2%

Physical Done

DoneRemaining

Project Timeline

Awarded

06-04-2022

Construction Started

06-04-2022

In Progress

Near Completion

-

Completed

31-12-2026

Physical vs Financial Progress

Project Details

UPC

N/08038/03003/BR

National Highway

80

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

32.35 km

Contractor

Montecarlo Munger Mirzachauki 3 highway Private Limited

Project Stage

Under Construction (AD issued)

Drone Frames

2628 frames

Last Flight

2026-02-24

Cost & Timeline

Awarded Cost

₹1017.00 Cr

Capital Cost

₹1769.50 Cr

Start Date

06-04-2022

PCOD Date

-

Scheduled Completion

12-04-2024

Likely Completion

31-12-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-06-16 11:25:29

Contractor Profile

Montecarlo Munger Mirzachauki 3 highway Private Limited

RO-Patna80HAM

Project Intelligence

1

Project is more than halfway complete at 72.2% physical progress.

2

Project is on schedule or ahead of planned completion date.

3

Covers 32.35 km on 80, improving regional connectivity.

4

2628 drone frames uploaded — real-time aerial monitoring is active for this project.

4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3) is a National Highways Authority of India (NHAI) project on 80 in Bihar. The project has an awarded cost of ₹1017.00 Cr and is currently ongoing with physical progress at 72.2%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

2,628 frames · NHAI surveillance footage · UPC N/08038/03003/BR

View Drone Images

Frequently Asked Questions

What is the current status of the NHAI project "4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Ra"?
Current physical progress: 72.2%. Financial progress: 32.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 12-04-2024. Likely completion: 31-12-2026.
Who is the contractor for this NHAI highway project?
The contractor for 4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3) is Montecarlo Munger Mirzachauki 3 highway Private Limited. The project is under RO-Patna and covers 32.35 km on 80.
What is the cost of this NHAI highway project?
The awarded cost is ₹1017.00 Crore. Total capital cost: ₹1769.50 Crore. The project is on 80 in Bihar, monitored via drone surveillance by NHAI.
What is UPC N/08038/03003/BR in NHAI?
UPC (Unique Project Code) N/08038/03003/BR refers to "4L of Munger – Mirzachauki section from start of existing Bhagalpur bypass to Rasulpur from Km 125+000 to Km 157+350 (Pkg-3)" — a National Highway project on 80 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.