4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4)
Physical Progress
90.7%
Drone-monitored
Financial Progress
40.0%
Of awarded cost
Awarded Cost
₹892 Cr
Contract value
Length
36.58 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2963
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
15-08-2024
Likely Date
31-08-2026
Completion
90.7%
Physical Done
Project Timeline
Awarded
17-08-2022
Construction Started
17-08-2022
In Progress
Near Completion
-
Completed
31-08-2026
Physical vs Financial Progress
Project Details
UPC
N/08038/03001/BR
National Highway
80
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
36.58 km
Contractor
APCO Infratech Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
2963 frames
Last Flight
2026-02-24
Cost & Timeline
Awarded Cost
₹892.00 Cr
Capital Cost
₹1376.56 Cr
Start Date
17-08-2022
PCOD Date
-
Scheduled Completion
15-08-2024
Likely Completion
31-08-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 11:04:32
Contractor Profile
APCO Infratech Pvt. Ltd.
Project Intelligence
Construction is 90.7% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 36.58 km on 80, improving regional connectivity.
2963 drone frames uploaded — real-time aerial monitoring is active for this project.
4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4) is a National Highways Authority of India (NHAI) project on 80 in Bihar. The project has an awarded cost of ₹892.00 Cr and is currently ongoing with physical progress at 90.7%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
2,963 frames · NHAI surveillance footage · UPC N/08038/03001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4)"?
- Current physical progress: 90.7%. Financial progress: 40.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 15-08-2024. Likely completion: 31-08-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4) is APCO Infratech Pvt. Ltd.. The project is under RO-Patna and covers 36.58 km on 80.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹892.00 Crore. Total capital cost: ₹1376.56 Crore. The project is on 80 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/08038/03001/BR in NHAI?
- UPC (Unique Project Code) N/08038/03001/BR refers to "4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4)" — a National Highway project on 80 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.