4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4)

UPC: N/08038/03001/BR

Physical Progress

92.0%

Drone-monitored

Financial Progress

89.5%

Of awarded cost

Awarded Cost

₹892 Cr

Contract value

Length

36.58 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

3153

Aerial captures

Project Progress

Physical Progress92.0%
Financial Progress89.5%

Stage

Under Construction (AD issued)

Due Date

15-08-2024

Likely Date

31-10-2026

Completion

92.0%

Physical Done

DoneRemaining

Project Timeline

Awarded

17-08-2022

Construction Started

17-08-2022

In Progress

Near Completion

-

Completed

31-10-2026

Physical vs Financial Progress

Project Details

UPC

N/08038/03001/BR

National Highway

80

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

36.58 km

Contractor

APCO Infratech Pvt. Ltd.

Project Stage

Under Construction (AD issued)

Drone Frames

3153 frames

Last Flight

2026-07-27

Cost & Timeline

Awarded Cost

₹892.00 Cr

Capital Cost

₹1376.56 Cr

Start Date

17-08-2022

PCOD Date

-

Scheduled Completion

15-08-2024

Likely Completion

31-10-2026

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-08-29 09:28:37

Contractor Profile

APCO Infratech Pvt. Ltd.

RO-Patna80HAM

Project Intelligence

1

Construction is 92.0% complete — nearing final stages.

2

Project is on schedule or ahead of planned completion date.

3

Covers 36.58 km on 80, improving regional connectivity.

4

3153 drone frames uploaded — real-time aerial monitoring is active for this project.

4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4) is a National Highways Authority of India (NHAI) project on 80 in Bihar. The project has an awarded cost of ₹892.00 Cr and is currently ongoing with physical progress at 92.0%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

3,153 frames · NHAI surveillance footage · UPC N/08038/03001/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4)"?
Current physical progress: 92.0%. Financial progress: 89.5%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 15-08-2024. Likely completion: 31-10-2026.
QWho is the contractor for this NHAI highway project?
The contractor for 4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4) is APCO Infratech Pvt. Ltd.. The project is under RO-Patna and covers 36.58 km on 80.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹892.00 Crore. Total capital cost: ₹1376.56 Crore. The project is on 80 in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/08038/03001/BR in NHAI?
UPC (Unique Project Code) N/08038/03001/BR refers to "4L of Munger – Mirzachauki section from Km 157+350 to Km 193+931 (Pkg-4)" — a National Highway project on 80 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.