4L of Munger – Mirzachauki section from Munger to Kharia village junction from Km 69+520 to Km 95+580 (Pkg-1)
Physical Progress
85.2%
Drone-monitored
Financial Progress
82.7%
Of awarded cost
Awarded Cost
₹981 Cr
Contract value
Length
26.06 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
1969
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
30-03-2024
Likely Date
31-10-2026
Completion
85.2%
Physical Done
Project Timeline
Awarded
31-03-2022
Construction Started
31-03-2022
In Progress
Near Completion
-
Completed
31-10-2026
Physical vs Financial Progress
Project Details
UPC
N/08038/02001/BR
National Highway
80
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
26.06 km
Contractor
Montecarlo Munger Mirzachauki 1 Highway Private Limited
Project Stage
Under Construction (AD issued)
Drone Frames
1969 frames
Last Flight
2026-08-27
Cost & Timeline
Awarded Cost
₹981.00 Cr
Capital Cost
₹1659.81 Cr
Start Date
31-03-2022
PCOD Date
-
Scheduled Completion
30-03-2024
Likely Completion
31-10-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-13 18:49:18
Contractor Profile
Montecarlo Munger Mirzachauki 1 Highway Private Limited
Project Intelligence
Construction is 85.2% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 26.06 km on 80, improving regional connectivity.
1969 drone frames uploaded — real-time aerial monitoring is active for this project.
4L of Munger – Mirzachauki section from Munger to Kharia village junction from Km 69+520 to Km 95+580 (Pkg-1) is a National Highways Authority of India (NHAI) project on 80 in Bihar. The project has an awarded cost of ₹981.00 Cr and is currently ongoing with physical progress at 85.2%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
1,969 frames · NHAI surveillance footage · UPC N/08038/02001/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "4L of Munger – Mirzachauki section from Munger to Kharia village junction from K"?
- Current physical progress: 85.2%. Financial progress: 82.7%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 30-03-2024. Likely completion: 31-10-2026.
- QWho is the contractor for this NHAI highway project?
- The contractor for 4L of Munger – Mirzachauki section from Munger to Kharia village junction from Km 69+520 to Km 95+580 (Pkg-1) is Montecarlo Munger Mirzachauki 1 Highway Private Limited. The project is under RO-Patna and covers 26.06 km on 80.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹981.00 Crore. Total capital cost: ₹1659.81 Crore. The project is on 80 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/08038/02001/BR in NHAI?
- UPC (Unique Project Code) N/08038/02001/BR refers to "4L of Munger – Mirzachauki section from Munger to Kharia village junction from Km 69+520 to Km 95+580 (Pkg-1)" — a National Highway project on 80 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.