Physical Progress
78.1%
Drone-monitored
Financial Progress
35.0%
Of awarded cost
Awarded Cost
₹981 Cr
Contract value
Length
26.06 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2180
Aerial captures
Stage
Under Construction (AD issued)
Due Date
30-03-2024
Likely Date
31-10-2026
78.1%
Physical Done
Awarded
31-03-2022
Construction Started
31-03-2022
In Progress
Near Completion
-
Completed
31-10-2026
UPC
N/08038/02001/BR
National Highway
80
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
26.06 km
Contractor
Montecarlo Munger Mirzachauki 1 Highway Private Limited
Project Stage
Under Construction (AD issued)
Drone Frames
2180 frames
Last Flight
2026-02-24
Awarded Cost
₹981.00 Cr
Capital Cost
₹1659.81 Cr
Start Date
31-03-2022
PCOD Date
-
Scheduled Completion
30-03-2024
Likely Completion
31-10-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 10:56:44
Montecarlo Munger Mirzachauki 1 Highway Private Limited
Project is more than halfway complete at 78.1% physical progress.
Project is on schedule or ahead of planned completion date.
Covers 26.06 km on 80, improving regional connectivity.
2180 drone frames uploaded — real-time aerial monitoring is active for this project.
2,180 frames · NHAI surveillance footage · UPC N/08038/02001/BR