4L of Munger – Mirzachauki section from Km 95+580 to Km 125+000 (Pkg-2)
Physical Progress
93.1%
Drone-monitored
Financial Progress
40.0%
Of awarded cost
Awarded Cost
₹902 Cr
Contract value
Length
29.42 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2428
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
10-03-2024
Likely Date
31-07-2026
Completion
93.1%
Physical Done
Project Timeline
Awarded
12-03-2022
Construction Started
12-03-2022
In Progress
Near Completion
-
Completed
31-07-2026
Physical vs Financial Progress
Project Details
UPC
N/08038/03002/BR
National Highway
80
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
29.42 km
Contractor
APCO Infratech Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
2428 frames
Last Flight
2026-02-24
Cost & Timeline
Awarded Cost
₹902.00 Cr
Capital Cost
₹1020.84 Cr
Start Date
12-03-2022
PCOD Date
-
Scheduled Completion
10-03-2024
Likely Completion
31-07-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 11:16:58
Contractor Profile
APCO Infratech Pvt. Ltd.
Project Intelligence
Construction is 93.1% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 29.42 km on 80, improving regional connectivity.
2428 drone frames uploaded — real-time aerial monitoring is active for this project.
4L of Munger – Mirzachauki section from Km 95+580 to Km 125+000 (Pkg-2) is a National Highways Authority of India (NHAI) project on 80 in Bihar. The project has an awarded cost of ₹902.00 Cr and is currently ongoing with physical progress at 93.1%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
2,428 frames · NHAI surveillance footage · UPC N/08038/03002/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L of Munger – Mirzachauki section from Km 95+580 to Km 125+000 (Pkg-2)"?
- Current physical progress: 93.1%. Financial progress: 40.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 10-03-2024. Likely completion: 31-07-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L of Munger – Mirzachauki section from Km 95+580 to Km 125+000 (Pkg-2) is APCO Infratech Pvt. Ltd.. The project is under RO-Patna and covers 29.42 km on 80.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹902.00 Crore. Total capital cost: ₹1020.84 Crore. The project is on 80 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/08038/03002/BR in NHAI?
- UPC (Unique Project Code) N/08038/03002/BR refers to "4L of Munger – Mirzachauki section from Km 95+580 to Km 125+000 (Pkg-2)" — a National Highway project on 80 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.