Physical Progress
93.1%
Drone-monitored
Financial Progress
40.0%
Of awarded cost
Awarded Cost
₹902 Cr
Contract value
Length
29.42 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2428
Aerial captures
Stage
Under Construction (AD issued)
Due Date
10-03-2024
Likely Date
31-07-2026
93.1%
Physical Done
Awarded
12-03-2022
Construction Started
12-03-2022
In Progress
Near Completion
-
Completed
31-07-2026
UPC
N/08038/03002/BR
National Highway
80
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
29.42 km
Contractor
APCO Infratech Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
2428 frames
Last Flight
2026-02-24
Awarded Cost
₹902.00 Cr
Capital Cost
₹1020.84 Cr
Start Date
12-03-2022
PCOD Date
-
Scheduled Completion
10-03-2024
Likely Completion
31-07-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 11:16:58
APCO Infratech Pvt. Ltd.
Construction is 93.1% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 29.42 km on 80, improving regional connectivity.
2428 drone frames uploaded — real-time aerial monitoring is active for this project.
2,428 frames · NHAI surveillance footage · UPC N/08038/03002/BR