Physical Progress
99.5%
Drone-monitored
Financial Progress
95.5%
Of awarded cost
Awarded Cost
₹2367 Cr
Contract value
Length
63.17 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
3405
Aerial captures
Stage
PCC Issued, CC Pending
Due Date
06-02-2013
Likely Date
31-07-2026
99.5%
Physical Done
Awarded
12-08-2010
Construction Started
12-08-2010
In Progress
Near Completion
01-09-2016
Completed
31-07-2026
UPC
N/05014/01001/BR
National Highway
22
Regional Office
RO-Patna
State
Bihar
Mode
BOT Annuity
Length
63.17 km
Contractor
Gammon Infrastructrure Projects Ltd.
Project Stage
PCC Issued, CC Pending
Drone Frames
3405 frames
Last Flight
2026-01-27
Awarded Cost
₹2367.00 Cr
Capital Cost
₹2723.39 Cr
Start Date
12-08-2010
PCOD Date
01-09-2016
Scheduled Completion
06-02-2013
Likely Completion
31-07-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 10:20:03
Gammon Infrastructrure Projects Ltd.
This is a mega infrastructure project worth ₹2367 Cr — among the largest NHAI projects in the region.
Construction is 99.5% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 63.17 km on 22, improving regional connectivity.
3405 drone frames uploaded — real-time aerial monitoring is active for this project.
3,405 frames · NHAI surveillance footage · UPC N/05014/01001/BR