Construction of Service Road, Drain, Junction Development in the stretch of Hajipur- Muzaffarpur in the state of Bihar on EPC Mode.
Physical Progress
0.0%
Drone-monitored
Financial Progress
0.0%
Of awarded cost
Awarded Cost
₹12 Cr
Contract value
Length
3.43 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
N/A
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
03-09-2026
Likely Date
-
Completion
0.0%
Physical Done
Project Timeline
Awarded
04-05-2026
Construction Started
04-05-2026
In Progress
Near Completion
-
Completed
-
Physical vs Financial Progress
Project Details
UPC
N/05014/01005/BR
National Highway
22
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
3.43 km
Contractor
Siddharth Construction
Project Stage
Under Construction (AD issued)
Drone Frames
N/A
Last Flight
N/A
Cost & Timeline
Awarded Cost
₹12.40 Cr
Capital Cost
N/A
Start Date
04-05-2026
PCOD Date
-
Scheduled Completion
03-09-2026
Likely Completion
-
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-09-20 21:43:36
Contractor Profile
Siddharth Construction
Project Intelligence
Physical progress stands at 0.0%. Financial utilization at 0.0%.
Project is on schedule or ahead of planned completion date.
Covers 3.43 km on 22, improving regional connectivity.
Construction of Service Road, Drain, Junction Development in the stretch of Hajipur- Muzaffarpur in the state of Bihar on EPC Mode. is a National Highways Authority of India (NHAI) project on 22 in Bihar. The project has an awarded cost of ₹12.40 Cr and is currently ongoing with physical progress at 0.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Frequently Asked Questions
- QWhat is the current status of the NHAI project "Construction of Service Road, Drain, Junction Development in the stretch of Haji"?
- Current physical progress: 0.0%. Financial progress: 0.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 03-09-2026. Likely completion: -.
- QWho is the contractor for this NHAI highway project?
- The contractor for Construction of Service Road, Drain, Junction Development in the stretch of Hajipur- Muzaffarpur in the state of Bihar on EPC Mode. is Siddharth Construction. The project is under RO-Patna and covers 3.43 km on 22.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹12.40 Crore. The project is on 22 in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/05014/01005/BR in NHAI?
- UPC (Unique Project Code) N/05014/01005/BR refers to "Construction of Service Road, Drain, Junction Development in the stretch of Hajipur- Muzaffarpur in the state of Bihar on EPC Mode." — a National Highway project on 22 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.