Yeshvanthpur - Channasandra Doubling Project [21.70 Km]
Original Cost
₹314 Cr
Baseline estimate
Revised Cost
₹684 Cr
Latest approved cost
Expenditure
₹174 Cr
Spent to date
Utilization
25.4%
Of revised budget
Cost Status
+117.7%
+₹370 Cr increase
Remaining
₹510 Cr
Budget left
Budget Utilization
25.4%Spent
₹174 Cr
Remaining
₹510 Cr
Total
₹684 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹314 Cr
Revised Cost
₹684 Cr
Increase
+₹370 Cr
Escalation
+117.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2024
Revised Completion
31/03/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹370 Cr (117.7%) from the original estimate of ₹314 Cr.
Expenditure stands at ₹174 Cr, which is 25.4% of the revised project cost.
Remaining budget: ₹510 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Yeshvanthpur - Channasandra Doubling Project [21.70 Km] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹314.00 Cr, later revised to ₹683.57 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Yeshvanthpur - Channasandra Doubling Project [21.70 Km]"?
- Yeshvanthpur - Channasandra Doubling Project [21.70 Km] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Karnataka. Original cost: ₹314 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹314 Cr and has been revised to ₹684 Cr — a cost overrun of +117.7%. Expenditure to date: ₹174 Cr (25.4% of revised cost). Data as of 2026-06.
- QWhich ministry is responsible for this project?
- Yeshvanthpur - Channasandra Doubling Project [21.70 Km] is under the Ministry of Railways in the Railways sector. Project code: 703585. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Yeshvanthpur - Channasandra Doubling Project [21.70 Km] is one of several Bihar projects tracked under the Railways sector on the IPM system.