Original Cost
₹314 Cr
Baseline estimate
Revised Cost
₹684 Cr
Latest approved cost
Expenditure
₹174 Cr
Spent to date
Utilization
25.4%
Of revised budget
Cost Status
+117.7%
+₹370 Cr increase
Remaining
₹510 Cr
Budget left
Spent
₹174 Cr
Remaining
₹510 Cr
Total
₹684 Cr
Original Cost
₹314 Cr
Revised Cost
₹684 Cr
Increase
+₹370 Cr
Escalation
+117.7%
Project Approved
Construction / Implementation
Original End Date
31/03/2024
Revised Completion
31/03/2026
Completed
Cost has increased by ₹370 Cr (117.7%) from the original estimate of ₹314 Cr.
Expenditure stands at ₹174 Cr, which is 25.4% of the revised project cost.
Remaining budget: ₹510 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.