RailwaysIPM · Central Project +117.7% overrun#703585

Yeshvanthpur - Channasandra Doubling Project [21.70 Km]

Ministry of RailwaysKarnataka
Revised Cost: ₹684 CrUtilization: 25.4%Overrun: +₹370 Cr

Original Cost

₹314 Cr

Baseline estimate

+118% overrun

Revised Cost

₹684 Cr

Latest approved cost

Expenditure

₹174 Cr

Spent to date

Utilization

25.4%

Of revised budget

Escalated

Cost Status

+117.7%

+₹370 Cr increase

Remaining

₹510 Cr

Budget left

Budget Utilization

25.4%
0%25%50%75%100%

Spent

₹174 Cr

Remaining

₹510 Cr

Total

₹684 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹314 Cr

Revised Cost

₹684 Cr

Increase

+₹370 Cr

Escalation

+117.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2024

Revised Completion

31/03/2026

Completed

Project Details

Project Code703585
SectorRailways
MinistryMinistry of Railways
StateKarnataka
Data Month2026-06

Financial Summary

Original Cost₹314 Cr
Revised Cost₹684 Cr
Expenditure₹174 Cr
Original End Date31/03/2024
Revised Date31/03/2026

Project Intelligence

Cost has increased by ₹370 Cr (117.7%) from the original estimate of ₹314 Cr.

Expenditure stands at ₹174 Cr, which is 25.4% of the revised project cost.

Remaining budget: ₹510 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Yeshvanthpur - Channasandra Doubling Project [21.70 Km] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹314.00 Cr, later revised to ₹683.57 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Yeshvanthpur - Channasandra Doubling Project [21.70 Km]"?
Yeshvanthpur - Channasandra Doubling Project [21.70 Km] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Karnataka. Original cost: ₹314 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹314 Cr and has been revised to ₹684 Cr — a cost overrun of +117.7%. Expenditure to date: ₹174 Cr (25.4% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Yeshvanthpur - Channasandra Doubling Project [21.70 Km] is under the Ministry of Railways in the Railways sector. Project code: 703585. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Yeshvanthpur - Channasandra Doubling Project [21.70 Km] is one of several Bihar projects tracked under the Railways sector on the IPM system.