Yekkambi-Haveri
Original Cost
₹295 Cr
Baseline estimate
Revised Cost
₹310 Cr
Latest approved cost
Expenditure
₹95 Cr
Spent to date
Utilization
30.6%
Of revised budget
Cost Status
+5.1%
+₹15 Cr increase
Remaining
₹215 Cr
Budget left
Budget Utilization
30.6%Spent
₹95 Cr
Remaining
₹215 Cr
Total
₹310 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹295 Cr
Revised Cost
₹310 Cr
Increase
+₹15 Cr
Escalation
+5.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
07/03/2024
Revised Completion
31/03/2028
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹15 Cr (5.1%) from the original estimate of ₹295 Cr.
Expenditure stands at ₹95 Cr, which is 30.6% of the revised project cost.
Remaining budget: ₹215 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Yekkambi-Haveri is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹295.00 Cr, later revised to ₹309.90 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Yekkambi-Haveri"?
- Yekkambi-Haveri is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹295 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹295 Cr and has been revised to ₹310 Cr — a cost overrun of +5.1%. Expenditure to date: ₹95 Cr (30.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Yekkambi-Haveri is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619138. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Yekkambi-Haveri is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.