Roads & HighwaysIPM · Central Project +5.1% overrun#619138

Yekkambi-Haveri

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹310 CrUtilization: 30.6%Overrun: +₹15 Cr

Original Cost

₹295 Cr

Baseline estimate

+5% overrun

Revised Cost

₹310 Cr

Latest approved cost

Expenditure

₹95 Cr

Spent to date

Utilization

30.6%

Of revised budget

Escalated

Cost Status

+5.1%

+₹15 Cr increase

Remaining

₹215 Cr

Budget left

Budget Utilization

30.6%
0%25%50%75%100%

Spent

₹95 Cr

Remaining

₹215 Cr

Total

₹310 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹295 Cr

Revised Cost

₹310 Cr

Increase

+₹15 Cr

Escalation

+5.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

07/03/2024

Revised Completion

31/03/2028

Completed

Project Details

Project Code619138
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹295 Cr
Revised Cost₹310 Cr
Expenditure₹95 Cr
Original End Date07/03/2024
Revised Date31/03/2028

Project Intelligence

Cost has increased by ₹15 Cr (5.1%) from the original estimate of ₹295 Cr.

Expenditure stands at ₹95 Cr, which is 30.6% of the revised project cost.

Remaining budget: ₹215 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Yekkambi-Haveri is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹295.00 Cr, later revised to ₹309.90 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Yekkambi-Haveri"?
Yekkambi-Haveri is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹295 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹295 Cr and has been revised to ₹310 Cr — a cost overrun of +5.1%. Expenditure to date: ₹95 Cr (30.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Yekkambi-Haveri is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619138. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Yekkambi-Haveri is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.