Original Cost
₹310 Cr
Baseline estimate
Revised Cost
₹310 Cr
Latest approved cost
Expenditure
₹82 Cr
Spent to date
Utilization
26.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹228 Cr
Budget left
Spent
₹82 Cr
Remaining
₹228 Cr
Total
₹310 Cr
Project Approved
Construction / Implementation
Original End Date
07/03/2024
Revised Completion
31/12/2027
Completed
Project is within original budget of ₹310 Cr — no cost escalation recorded.
Expenditure stands at ₹82 Cr, which is 26.6% of the revised project cost.
Remaining budget: ₹228 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.