Original Cost
₹782 Cr
Baseline estimate
Revised Cost
₹782 Cr
Latest approved cost
Expenditure
₹21 Cr
Spent to date
Utilization
2.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹761 Cr
Budget left
Spent
₹21 Cr
Remaining
₹761 Cr
Total
₹782 Cr
Project Approved
Construction / Implementation
Original End Date
06/12/2026
Revised Completion
03/07/2027
Completed
Project is within original budget of ₹782 Cr — no cost escalation recorded.
Expenditure stands at ₹21 Cr, which is 2.7% of the revised project cost.
Remaining budget: ₹761 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.