2-laning of Zorinpui - Longmasu section of NH-502A from km 0.000 to km 28.244 in the State of Mizoram on EPC mode under NHO-NE, stretch of IMBR
Original Cost
₹782 Cr
Baseline estimate
Revised Cost
₹782 Cr
Latest approved cost
Expenditure
₹48 Cr
Spent to date
Utilization
6.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹734 Cr
Budget left
Budget Utilization
6.2%Spent
₹48 Cr
Remaining
₹734 Cr
Total
₹782 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
06/12/2026
Revised Completion
31/12/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹782 Cr — no cost escalation recorded.
Expenditure stands at ₹48 Cr, which is 6.2% of the revised project cost.
Remaining budget: ₹734 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
2-laning of Zorinpui - Longmasu section of NH-502A from km 0.000 to km 28.244 in the State of Mizoram on EPC mode under NHO-NE, stretch of IMBR is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹782.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "2-laning of Zorinpui - Longmasu section of NH-502A from km 0.000 to km 28.244 in"?
- 2-laning of Zorinpui - Longmasu section of NH-502A from km 0.000 to km 28.244 in the State of Mizoram on EPC mode under NHO-NE, stretch of IMBR is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Mizoram. Original cost: ₹782 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹782 Cr has not been significantly revised. Expenditure: ₹48 Cr (6.2% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 2-laning of Zorinpui - Longmasu section of NH-502A from km 0 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618452. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 2-laning of Zorinpui - Longmasu section of NH-502A from km 0 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.