Original Cost
₹961 Cr
Baseline estimate
Revised Cost
₹644 Cr
Latest approved cost
Expenditure
₹431 Cr
Spent to date
Utilization
66.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹213 Cr
Budget left
Spent
₹431 Cr
Remaining
₹213 Cr
Total
₹644 Cr
Project Approved
Construction / Implementation
Original End Date
25/06/2026
Revised Completion
15/06/2027
Completed
Project is within original budget of ₹961 Cr — no cost escalation recorded.
Expenditure stands at ₹431 Cr, which is 66.9% of the revised project cost.
Remaining budget: ₹213 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.