Roads & HighwaysIPM · Central Project#617976

Work of development and construction of elevated corridorfrom km 38/660 to km 42/690 Iscon junction to start point of approach of sanand flyover of NH-147 in the sate of Gujarat

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹530 CrUtilization: 71.7%

Original Cost

₹530 Cr

Baseline estimate

On budget

Revised Cost

₹530 Cr

Latest approved cost

Expenditure

₹380 Cr

Spent to date

Utilization

71.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹150 Cr

Budget left

Budget Utilization

71.7%
0%25%50%75%100%

Spent

₹380 Cr

Remaining

₹150 Cr

Total

₹530 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

18/06/2026

Revised Completion

30/09/2026

Completed

Project Details

Project Code617976
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹530 Cr
Revised Cost₹530 Cr
Expenditure₹380 Cr
Original End Date18/06/2026
Revised Date30/09/2026

Project Intelligence

Project is within original budget of ₹530 Cr — no cost escalation recorded.

Expenditure stands at ₹380 Cr, which is 71.7% of the revised project cost.

Remaining budget: ₹150 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Work of development and construction of elevated corridorfrom km 38/660 to km 42/690 Iscon junction to start point of approach of sanand flyover of NH-147 in the sate of Gujarat is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹530.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Work of development and construction of elevated corridorfrom km 38/660 to km 42"?
Work of development and construction of elevated corridorfrom km 38/660 to km 42/690 Iscon junction to start point of approach of sanand flyover of NH-147 in the sate of Gujarat is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹530 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹530 Cr has not been significantly revised. Expenditure: ₹380 Cr (71.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Work of development and construction of elevated corridorfro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617976. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Work of development and construction of elevated corridorfro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.