Roads & HighwaysIPM · Central Project#618309

Widening/lmprovement to 4-Laning and Greenfield alignment with Paved shoulder of Silchar-Badarpur Churaibari section of NH-37 & NH-8 from Design chainage 38.600 End point of proposed Badarpur Bypass to Km. 62.800 Start point of proposed Nilambazar/Cheragi Bypass in the state of Assam on HAM Mode Package-4

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹1320 CrUtilization: 14.0%

Original Cost

₹1320 Cr

Baseline estimate

On budget

Revised Cost

₹1320 Cr

Latest approved cost

Expenditure

₹185 Cr

Spent to date

Utilization

14.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1135 Cr

Budget left

Budget Utilization

14.0%
0%25%50%75%100%

Spent

₹185 Cr

Remaining

₹1135 Cr

Total

₹1320 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

18/08/2027

Revised Completion

18/08/2027

Completed

Project Details

Project Code618309
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-08

Financial Summary

Original Cost₹1320 Cr
Revised Cost₹1320 Cr
Expenditure₹185 Cr
Original End Date18/08/2027
Revised Date18/08/2027

Project Intelligence

Project is within original budget of ₹1320 Cr — no cost escalation recorded.

Expenditure stands at ₹185 Cr, which is 14.0% of the revised project cost.

Remaining budget: ₹1135 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening/lmprovement to 4-Laning and Greenfield alignment with Paved shoulder of Silchar-Badarpur Churaibari section of NH-37 & NH-8 from Design chainage 38.600 End point of proposed Badarpur Bypass to Km. 62.800 Start point of proposed Nilambazar/Cheragi Bypass in the state of Assam on HAM Mode Package-4 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1320.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening/lmprovement to 4-Laning and Greenfield alignment with Paved shoulder of"?
Widening/lmprovement to 4-Laning and Greenfield alignment with Paved shoulder of Silchar-Badarpur Churaibari section of NH-37 & NH-8 from Design chainage 38.600 End point of proposed Badarpur Bypass to Km. 62.800 Start point of proposed Nilambazar/Cheragi Bypass in the state of Assam on HAM Mode Package-4 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹1320 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1320 Cr has not been significantly revised. Expenditure: ₹185 Cr (14.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening/lmprovement to 4-Laning and Greenfield alignment wi is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618309. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening/lmprovement to 4-Laning and Greenfield alignment wi is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.