Roads & HighwaysIPM · Central Project#618303

Widening/Improvement to 2-lane with earthen shoulder of Yaingangpokpi - Finch corner road section of NH-202 from Km 0.000 to Km 16.900 of NH-202 in the state of Manipur on EPC mode Package-1

Ministry of Road Transport & HighwaysManipur
Revised Cost: ₹223 CrUtilization: 63.2%

Original Cost

₹223 Cr

Baseline estimate

On budget

Revised Cost

₹223 Cr

Latest approved cost

Expenditure

₹141 Cr

Spent to date

Utilization

63.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹82 Cr

Budget left

Budget Utilization

63.2%
0%25%50%75%100%

Spent

₹141 Cr

Remaining

₹82 Cr

Total

₹223 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/06/2022

Revised Completion

31/10/2026

Completed

Project Details

Project Code618303
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateManipur
Data Month2026-08

Financial Summary

Original Cost₹223 Cr
Revised Cost₹223 Cr
Expenditure₹141 Cr
Original End Date30/06/2022
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹223 Cr — no cost escalation recorded.

Expenditure stands at ₹141 Cr, which is 63.2% of the revised project cost.

Remaining budget: ₹82 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening/Improvement to 2-lane with earthen shoulder of Yaingangpokpi - Finch corner road section of NH-202 from Km 0.000 to Km 16.900 of NH-202 in the state of Manipur on EPC mode Package-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹223.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening/Improvement to 2-lane with earthen shoulder of Yaingangpokpi - Finch co"?
Widening/Improvement to 2-lane with earthen shoulder of Yaingangpokpi - Finch corner road section of NH-202 from Km 0.000 to Km 16.900 of NH-202 in the state of Manipur on EPC mode Package-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Manipur. Original cost: ₹223 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹223 Cr has not been significantly revised. Expenditure: ₹141 Cr (63.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening/Improvement to 2-lane with earthen shoulder of Yain is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618303. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening/Improvement to 2-lane with earthen shoulder of Yain is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.