Widening/Improvement to 2 lane with earthen shoulder of Choithar to Marrem Khullen section of NH-202 of Imphal Ukhrul Jessami Economic Corridor from Design Chainage km 53.110 to km 95.700 in the State of Manipur on EPC mode under Bharatmala Pariyojana, under NHO-NE Package-5
Original Cost
₹564 Cr
Baseline estimate
Revised Cost
₹564 Cr
Latest approved cost
Expenditure
₹174 Cr
Spent to date
Utilization
30.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹390 Cr
Budget left
Budget Utilization
30.8%Spent
₹174 Cr
Remaining
₹390 Cr
Total
₹564 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2027
Revised Completion
31/08/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹564 Cr — no cost escalation recorded.
Expenditure stands at ₹174 Cr, which is 30.8% of the revised project cost.
Remaining budget: ₹390 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening/Improvement to 2 lane with earthen shoulder of Choithar to Marrem Khullen section of NH-202 of Imphal Ukhrul Jessami Economic Corridor from Design Chainage km 53.110 to km 95.700 in the State of Manipur on EPC mode under Bharatmala Pariyojana, under NHO-NE Package-5 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹564.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening/Improvement to 2 lane with earthen shoulder of Choithar to Marrem Khull"?
- Widening/Improvement to 2 lane with earthen shoulder of Choithar to Marrem Khullen section of NH-202 of Imphal Ukhrul Jessami Economic Corridor from Design Chainage km 53.110 to km 95.700 in the State of Manipur on EPC mode under Bharatmala Pariyojana, under NHO-NE Package-5 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Manipur. Original cost: ₹564 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹564 Cr has not been significantly revised. Expenditure: ₹174 Cr (30.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening/Improvement to 2 lane with earthen shoulder of Choi is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618306. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening/Improvement to 2 lane with earthen shoulder of Choi is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.