Original Cost
₹229 Cr
Baseline estimate
Revised Cost
₹229 Cr
Latest approved cost
Expenditure
₹34 Cr
Spent to date
Utilization
14.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹195 Cr
Budget left
Spent
₹34 Cr
Remaining
₹195 Cr
Total
₹229 Cr
Project Approved
Construction / Implementation
Original End Date
27/08/2026
Revised Completion
27/08/2026
Completed
Project is within original budget of ₹229 Cr — no cost escalation recorded.
Expenditure stands at ₹34 Cr, which is 14.7% of the revised project cost.
Remaining budget: ₹195 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.