Widening & Upgradation to 2 lanes with paved shoulders road from Tamenglong to Mahur NH-137 in the State of Assam starting from km 136.500 near Hejaichak to km 156.489 near P. Leikul Package-9 on EPC mode under NHO-NE Package-9
Original Cost
₹860 Cr
Baseline estimate
Revised Cost
₹614 Cr
Latest approved cost
Expenditure
₹560 Cr
Spent to date
Utilization
91.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹55 Cr
Budget left
Budget Utilization
91.1%Spent
₹560 Cr
Remaining
₹55 Cr
Total
₹614 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
29/08/2025
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹860 Cr — no cost escalation recorded.
Expenditure stands at ₹560 Cr, which is 91.1% of the revised project cost.
Remaining budget: ₹55 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening & Upgradation to 2 lanes with paved shoulders road from Tamenglong to Mahur NH-137 in the State of Assam starting from km 136.500 near Hejaichak to km 156.489 near P. Leikul Package-9 on EPC mode under NHO-NE Package-9 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹860.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening & Upgradation to 2 lanes with paved shoulders road from Tamenglong to M"?
- Widening & Upgradation to 2 lanes with paved shoulders road from Tamenglong to Mahur NH-137 in the State of Assam starting from km 136.500 near Hejaichak to km 156.489 near P. Leikul Package-9 on EPC mode under NHO-NE Package-9 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹860 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹860 Cr and has been revised to ₹614 Cr — a cost overrun of -28.6%. Expenditure to date: ₹560 Cr (91.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening & Upgradation to 2 lanes with paved shoulders road is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618352. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening & Upgradation to 2 lanes with paved shoulders road is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.