Roads & HighwaysIPM · Central Project#618410

Widening & Up-gradation to 2 lane with paved shoulder of NH-301 Kargil- Zanskar Road from Design Km .30.040 Ex. Km. 30.000 to Design Km 57.000 Ex. Km. 57.905 of 26.960 Km length Pkg-II

Ministry of Road Transport & HighwaysLadakh
Revised Cost: ₹405 CrUtilization: 93.2%

Original Cost

₹405 Cr

Baseline estimate

On budget

Revised Cost

₹405 Cr

Latest approved cost

Expenditure

₹378 Cr

Spent to date

Utilization

93.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹27 Cr

Budget left

Budget Utilization

93.2%
0%25%50%75%100%

Spent

₹378 Cr

Remaining

₹27 Cr

Total

₹405 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

02/01/2023

Revised Completion

05/10/2026

Completed

Project Details

Project Code618410
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateLadakh
Data Month2026-08

Financial Summary

Original Cost₹405 Cr
Revised Cost₹405 Cr
Expenditure₹378 Cr
Original End Date02/01/2023
Revised Date05/10/2026

Project Intelligence

Project is within original budget of ₹405 Cr — no cost escalation recorded.

Expenditure stands at ₹378 Cr, which is 93.2% of the revised project cost.

Remaining budget: ₹27 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening & Up-gradation to 2 lane with paved shoulder of NH-301 Kargil- Zanskar Road from Design Km .30.040 Ex. Km. 30.000 to Design Km 57.000 Ex. Km. 57.905 of 26.960 Km length Pkg-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹405.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening & Up-gradation to 2 lane with paved shoulder of NH-301 Kargil- Zanskar "?
Widening & Up-gradation to 2 lane with paved shoulder of NH-301 Kargil- Zanskar Road from Design Km .30.040 Ex. Km. 30.000 to Design Km 57.000 Ex. Km. 57.905 of 26.960 Km length Pkg-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Ladakh. Original cost: ₹405 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹405 Cr has not been significantly revised. Expenditure: ₹378 Cr (93.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening & Up-gradation to 2 lane with paved shoulder of NH- is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618410. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening & Up-gradation to 2 lane with paved shoulder of NH- is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.