Widening to Two with Paved shoulders from Km 59.500 to Km 132.033 of Manneguda- Ravunapally section of NH-163 Erstwhile SH-4 in the State of Telangana on EPC mode under NH O Annual Plan 2016-17
Original Cost
₹359 Cr
Baseline estimate
Revised Cost
₹359 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹359 Cr
Budget left
Budget Utilization
0.0%Spent
₹0 Cr
Remaining
₹359 Cr
Total
₹359 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
11/05/2019
Revised Completion
31/05/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹359 Cr — no cost escalation recorded.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹359 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to Two with Paved shoulders from Km 59.500 to Km 132.033 of Manneguda- Ravunapally section of NH-163 Erstwhile SH-4 in the State of Telangana on EPC mode under NH O Annual Plan 2016-17 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹359.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to Two with Paved shoulders from Km 59.500 to Km 132.033 of Manneguda- "?
- Widening to Two with Paved shoulders from Km 59.500 to Km 132.033 of Manneguda- Ravunapally section of NH-163 Erstwhile SH-4 in the State of Telangana on EPC mode under NH O Annual Plan 2016-17 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹359 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹359 Cr has not been significantly revised. Expenditure: ₹0 Cr (N/A% of cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- Widening to Two with Paved shoulders from Km 59.500 to Km 13 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617981. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to Two with Paved shoulders from Km 59.500 to Km 13 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.