Widening to two lane with paved shoulders of 'Bodhan Basar Bhainsa ' section from Km 38/900 to 95/300 of NH-161BB in the state of Telangana under Annual Plan 2021-22 on EPC Mode under NH O.
Original Cost
₹644 Cr
Baseline estimate
Revised Cost
₹644 Cr
Latest approved cost
Expenditure
₹460 Cr
Spent to date
Utilization
71.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹184 Cr
Budget left
Budget Utilization
71.4%Spent
₹460 Cr
Remaining
₹184 Cr
Total
₹644 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
16/03/2025
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹644 Cr — no cost escalation recorded.
Expenditure stands at ₹460 Cr, which is 71.4% of the revised project cost.
Remaining budget: ₹184 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to two lane with paved shoulders of 'Bodhan Basar Bhainsa ' section from Km 38/900 to 95/300 of NH-161BB in the state of Telangana under Annual Plan 2021-22 on EPC Mode under NH O. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹644.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to two lane with paved shoulders of 'Bodhan Basar Bhainsa ' section fro"?
- Widening to two lane with paved shoulders of 'Bodhan Basar Bhainsa ' section from Km 38/900 to 95/300 of NH-161BB in the state of Telangana under Annual Plan 2021-22 on EPC Mode under NH O. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹644 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹644 Cr has not been significantly revised. Expenditure: ₹460 Cr (71.4% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to two lane with paved shoulders of 'Bodhan Basar B is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618190. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to two lane with paved shoulders of 'Bodhan Basar B is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.