Widening to two lane with paved shoulders from Km 0/0 to 64/020 Pamarru to Akiveedu
Original Cost
₹530 Cr
Baseline estimate
Revised Cost
₹589 Cr
Latest approved cost
Expenditure
₹441 Cr
Spent to date
Utilization
74.9%
Of revised budget
Cost Status
+11.1%
+₹59 Cr increase
Remaining
₹148 Cr
Budget left
Budget Utilization
74.9%Spent
₹441 Cr
Remaining
₹148 Cr
Total
₹589 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹530 Cr
Revised Cost
₹589 Cr
Increase
+₹59 Cr
Escalation
+11.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
16/11/2023
Revised Completion
31/05/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹59 Cr (11.1%) from the original estimate of ₹530 Cr.
Expenditure stands at ₹441 Cr, which is 74.9% of the revised project cost.
Remaining budget: ₹148 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to two lane with paved shoulders from Km 0/0 to 64/020 Pamarru to Akiveedu is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹530.00 Cr, later revised to ₹588.65 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to two lane with paved shoulders from Km 0/0 to 64/020 Pamarru to Akive"?
- Widening to two lane with paved shoulders from Km 0/0 to 64/020 Pamarru to Akiveedu is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹530 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹530 Cr and has been revised to ₹589 Cr — a cost overrun of +11.1%. Expenditure to date: ₹441 Cr (74.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to two lane with paved shoulders from Km 0/0 to 64/ is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617985. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to two lane with paved shoulders from Km 0/0 to 64/ is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.