Original Cost
₹617 Cr
Baseline estimate
Revised Cost
₹617 Cr
Latest approved cost
Expenditure
₹5 Cr
Spent to date
Utilization
0.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹612 Cr
Budget left
Spent
₹5 Cr
Remaining
₹612 Cr
Total
₹617 Cr
Project Approved
Construction / Implementation
Original End Date
13/01/2027
Revised Completion
13/01/2027
Completed
Project is within original budget of ₹617 Cr — no cost escalation recorded.
Expenditure stands at ₹5 Cr, which is 0.8% of the revised project cost.
Remaining budget: ₹612 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.