Roads & HighwaysIPM · Central Project#618145

Widening to two lane with paved shoulder of Rampachodavaram - Koyyuru section of NH 516E from Km 43700 to Km 113820 in the State of Andhra Pradesh on EPC mode Job No. 737

Ministry of Road Transport & HighwaysAndhra Pradesh
Revised Cost: ₹568 CrUtilization: 53.4%

Original Cost

₹568 Cr

Baseline estimate

On budget

Revised Cost

₹568 Cr

Latest approved cost

Expenditure

₹303 Cr

Spent to date

Utilization

53.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹265 Cr

Budget left

Budget Utilization

53.4%
0%25%50%75%100%

Spent

₹303 Cr

Remaining

₹265 Cr

Total

₹568 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/01/2025

Revised Completion

30/04/2026

Completed

Project Details

Project Code618145
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAndhra Pradesh
Data Month2026-05

Financial Summary

Original Cost₹568 Cr
Revised Cost₹568 Cr
Expenditure₹303 Cr
Original End Date01/01/2025
Revised Date30/04/2026

Project Intelligence

Project is within original budget of ₹568 Cr — no cost escalation recorded.

Expenditure stands at ₹303 Cr, which is 53.4% of the revised project cost.

Remaining budget: ₹265 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening to two lane with paved shoulder of Rampachodavaram - Koyyuru section of NH 516E from Km 43700 to Km 113820 in the State of Andhra Pradesh on EPC mode Job No. 737 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹568.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening to two lane with paved shoulder of Rampachodavaram - Koyyuru section of"?
Widening to two lane with paved shoulder of Rampachodavaram - Koyyuru section of NH 516E from Km 43700 to Km 113820 in the State of Andhra Pradesh on EPC mode Job No. 737 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹568 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹568 Cr has not been significantly revised. Expenditure: ₹303 Cr (53.4% of cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Widening to two lane with paved shoulder of Rampachodavaram is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618145. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to two lane with paved shoulder of Rampachodavaram is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.