Roads & HighwaysIPM · Central Project#618087

Widening to intermediate/two lane to 2 lane with paved shoulder from Existing chanages Km 112.750 to 142.00 Liingasur to Mudabal cross & from Km. 147.070 to Km. 149.070 Maski city limit of Jewargi Chamrajnagar setion of NH-150A in the state of Karnataka on EPC mode. Job No. NH-150A-KNT-2021-22-951

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹256 CrUtilization: 78.8%

Original Cost

₹256 Cr

Baseline estimate

On budget

Revised Cost

₹256 Cr

Latest approved cost

Expenditure

₹202 Cr

Spent to date

Utilization

78.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹54 Cr

Budget left

Budget Utilization

78.8%
0%25%50%75%100%

Spent

₹202 Cr

Remaining

₹54 Cr

Total

₹256 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

17/07/2024

Revised Completion

30/09/2026

Completed

Project Details

Project Code618087
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹256 Cr
Revised Cost₹256 Cr
Expenditure₹202 Cr
Original End Date17/07/2024
Revised Date30/09/2026

Project Intelligence

Project is within original budget of ₹256 Cr — no cost escalation recorded.

Expenditure stands at ₹202 Cr, which is 78.8% of the revised project cost.

Remaining budget: ₹54 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening to intermediate/two lane to 2 lane with paved shoulder from Existing chanages Km 112.750 to 142.00 Liingasur to Mudabal cross & from Km. 147.070 to Km. 149.070 Maski city limit of Jewargi Chamrajnagar setion of NH-150A in the state of Karnataka on EPC mode. Job No. NH-150A-KNT-2021-22-951 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹256.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening to intermediate/two lane to 2 lane with paved shoulder from Existing ch"?
Widening to intermediate/two lane to 2 lane with paved shoulder from Existing chanages Km 112.750 to 142.00 Liingasur to Mudabal cross & from Km. 147.070 to Km. 149.070 Maski city limit of Jewargi Chamrajnagar setion of NH-150A in the state of Karnataka on EPC mode. Job No. NH-150A-KNT-2021-22-951 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹256 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹256 Cr has not been significantly revised. Expenditure: ₹202 Cr (78.8% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening to intermediate/two lane to 2 lane with paved shoul is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618087. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to intermediate/two lane to 2 lane with paved shoul is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.