Original Cost
₹256 Cr
Baseline estimate
Revised Cost
₹256 Cr
Latest approved cost
Expenditure
₹180 Cr
Spent to date
Utilization
70.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹76 Cr
Budget left
Spent
₹180 Cr
Remaining
₹76 Cr
Total
₹256 Cr
Project Approved
Construction / Implementation
Original End Date
17/07/2024
Revised Completion
31/08/2026
Completed
Project is within original budget of ₹256 Cr — no cost escalation recorded.
Expenditure stands at ₹180 Cr, which is 70.2% of the revised project cost.
Remaining budget: ₹76 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.