Widening to intermediate/two lane to 2 lane with paved shoulder from Existing chanages Km 112.750 to 142.00 Liingasur to Mudabal cross & from Km. 147.070 to Km. 149.070 Maski city limit of Jewargi Chamrajnagar setion of NH-150A in the state of Karnataka on EPC mode. Job No. NH-150A-KNT-2021-22-951
Original Cost
₹256 Cr
Baseline estimate
Revised Cost
₹256 Cr
Latest approved cost
Expenditure
₹202 Cr
Spent to date
Utilization
78.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹54 Cr
Budget left
Budget Utilization
78.8%Spent
₹202 Cr
Remaining
₹54 Cr
Total
₹256 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
17/07/2024
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹256 Cr — no cost escalation recorded.
Expenditure stands at ₹202 Cr, which is 78.8% of the revised project cost.
Remaining budget: ₹54 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to intermediate/two lane to 2 lane with paved shoulder from Existing chanages Km 112.750 to 142.00 Liingasur to Mudabal cross & from Km. 147.070 to Km. 149.070 Maski city limit of Jewargi Chamrajnagar setion of NH-150A in the state of Karnataka on EPC mode. Job No. NH-150A-KNT-2021-22-951 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹256.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to intermediate/two lane to 2 lane with paved shoulder from Existing ch"?
- Widening to intermediate/two lane to 2 lane with paved shoulder from Existing chanages Km 112.750 to 142.00 Liingasur to Mudabal cross & from Km. 147.070 to Km. 149.070 Maski city limit of Jewargi Chamrajnagar setion of NH-150A in the state of Karnataka on EPC mode. Job No. NH-150A-KNT-2021-22-951 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹256 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹256 Cr has not been significantly revised. Expenditure: ₹202 Cr (78.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to intermediate/two lane to 2 lane with paved shoul is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618087. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to intermediate/two lane to 2 lane with paved shoul is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.