Original Cost
₹356 Cr
Baseline estimate
Revised Cost
₹356 Cr
Latest approved cost
Expenditure
₹185 Cr
Spent to date
Utilization
51.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹171 Cr
Budget left
Spent
₹185 Cr
Remaining
₹171 Cr
Total
₹356 Cr
Project Approved
Construction / Implementation
Original End Date
26/12/2024
Revised Completion
30/11/2026
Completed
Project is within original budget of ₹356 Cr — no cost escalation recorded.
Expenditure stands at ₹185 Cr, which is 51.9% of the revised project cost.
Remaining budget: ₹171 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.