Widening to 4 lane from Km 51.60 to 76.20 Hebri to Parkala and from Km 85.20 to 88.90 Karavali junction to Malpe of Thirthahalli-Udupi-Malpe Section of NH-169A in the State of Karnataka on EPC Mode under Annual plan 2021-22 Job No. NH-169A-KNT-2021-22-927
Original Cost
₹356 Cr
Baseline estimate
Revised Cost
₹356 Cr
Latest approved cost
Expenditure
₹270 Cr
Spent to date
Utilization
75.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹86 Cr
Budget left
Budget Utilization
75.8%Spent
₹270 Cr
Remaining
₹86 Cr
Total
₹356 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
26/12/2024
Revised Completion
30/11/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹356 Cr — no cost escalation recorded.
Expenditure stands at ₹270 Cr, which is 75.8% of the revised project cost.
Remaining budget: ₹86 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to 4 lane from Km 51.60 to 76.20 Hebri to Parkala and from Km 85.20 to 88.90 Karavali junction to Malpe of Thirthahalli-Udupi-Malpe Section of NH-169A in the State of Karnataka on EPC Mode under Annual plan 2021-22 Job No. NH-169A-KNT-2021-22-927 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹356.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to 4 lane from Km 51.60 to 76.20 Hebri to Parkala and from Km 85.20 to "?
- Widening to 4 lane from Km 51.60 to 76.20 Hebri to Parkala and from Km 85.20 to 88.90 Karavali junction to Malpe of Thirthahalli-Udupi-Malpe Section of NH-169A in the State of Karnataka on EPC Mode under Annual plan 2021-22 Job No. NH-169A-KNT-2021-22-927 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹356 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹356 Cr has not been significantly revised. Expenditure: ₹270 Cr (75.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to 4 lane from Km 51.60 to 76.20 Hebri to Parkala a is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618109. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 4 lane from Km 51.60 to 76.20 Hebri to Parkala a is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.