Widening to 2LPS from Km 71.00 to 104.00 Existing chainages Sarjapur to Pattadkallu on Bhanapur to Gaddanakeri section NH-367 in the State of Karnataka under NHO on EPC mode under Annual Plan 2022-23 NH-367-KNT-2022-23-972 dated 08.02.2023
Original Cost
₹446 Cr
Baseline estimate
Revised Cost
₹446 Cr
Latest approved cost
Expenditure
₹256 Cr
Spent to date
Utilization
57.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹190 Cr
Budget left
Budget Utilization
57.3%Spent
₹256 Cr
Remaining
₹190 Cr
Total
₹446 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
15/03/2026
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹446 Cr — no cost escalation recorded.
Expenditure stands at ₹256 Cr, which is 57.3% of the revised project cost.
Remaining budget: ₹190 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to 2LPS from Km 71.00 to 104.00 Existing chainages Sarjapur to Pattadkallu on Bhanapur to Gaddanakeri section NH-367 in the State of Karnataka under NHO on EPC mode under Annual Plan 2022-23 NH-367-KNT-2022-23-972 dated 08.02.2023 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹446.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to 2LPS from Km 71.00 to 104.00 Existing chainages Sarjapur to Pattadka"?
- Widening to 2LPS from Km 71.00 to 104.00 Existing chainages Sarjapur to Pattadkallu on Bhanapur to Gaddanakeri section NH-367 in the State of Karnataka under NHO on EPC mode under Annual Plan 2022-23 NH-367-KNT-2022-23-972 dated 08.02.2023 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹446 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹446 Cr has not been significantly revised. Expenditure: ₹256 Cr (57.3% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to 2LPS from Km 71.00 to 104.00 Existing chainages is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618027. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2LPS from Km 71.00 to 104.00 Existing chainages is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.