Roads & HighwaysIPM · Central Project#618027

Widening to 2LPS from Km 71.00 to 104.00 Existing chainages Sarjapur to Pattadkallu on Bhanapur to Gaddanakeri section NH-367 in the State of Karnataka under NHO on EPC mode under Annual Plan 2022-23 NH-367-KNT-2022-23-972 dated 08.02.2023

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹446 CrUtilization: 57.3%

Original Cost

₹446 Cr

Baseline estimate

On budget

Revised Cost

₹446 Cr

Latest approved cost

Expenditure

₹256 Cr

Spent to date

Utilization

57.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹190 Cr

Budget left

Budget Utilization

57.3%
0%25%50%75%100%

Spent

₹256 Cr

Remaining

₹190 Cr

Total

₹446 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

15/03/2026

Revised Completion

31/12/2026

Completed

Project Details

Project Code618027
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹446 Cr
Revised Cost₹446 Cr
Expenditure₹256 Cr
Original End Date15/03/2026
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹446 Cr — no cost escalation recorded.

Expenditure stands at ₹256 Cr, which is 57.3% of the revised project cost.

Remaining budget: ₹190 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening to 2LPS from Km 71.00 to 104.00 Existing chainages Sarjapur to Pattadkallu on Bhanapur to Gaddanakeri section NH-367 in the State of Karnataka under NHO on EPC mode under Annual Plan 2022-23 NH-367-KNT-2022-23-972 dated 08.02.2023 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹446.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening to 2LPS from Km 71.00 to 104.00 Existing chainages Sarjapur to Pattadka"?
Widening to 2LPS from Km 71.00 to 104.00 Existing chainages Sarjapur to Pattadkallu on Bhanapur to Gaddanakeri section NH-367 in the State of Karnataka under NHO on EPC mode under Annual Plan 2022-23 NH-367-KNT-2022-23-972 dated 08.02.2023 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹446 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹446 Cr has not been significantly revised. Expenditure: ₹256 Cr (57.3% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening to 2LPS from Km 71.00 to 104.00 Existing chainages is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618027. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2LPS from Km 71.00 to 104.00 Existing chainages is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.