Widening to 2 Lane with Paved Shoulders from design Km 103.200 Existing Km 103.200 to design Km 116.700 Existing Km 118.470 on AP/KNT Border to Sira Section of NH-544E in the State of Karnatakaon EPC mode under Annual plan 2022-23
Original Cost
₹167 Cr
Baseline estimate
Revised Cost
₹167 Cr
Latest approved cost
Expenditure
₹85 Cr
Spent to date
Utilization
51.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹82 Cr
Budget left
Budget Utilization
51.2%Spent
₹85 Cr
Remaining
₹82 Cr
Total
₹167 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
09/09/2025
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹167 Cr — no cost escalation recorded.
Expenditure stands at ₹85 Cr, which is 51.2% of the revised project cost.
Remaining budget: ₹82 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to 2 Lane with Paved Shoulders from design Km 103.200 Existing Km 103.200 to design Km 116.700 Existing Km 118.470 on AP/KNT Border to Sira Section of NH-544E in the State of Karnatakaon EPC mode under Annual plan 2022-23 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹167.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to 2 Lane with Paved Shoulders from design Km 103.200 Existing Km 103.2"?
- Widening to 2 Lane with Paved Shoulders from design Km 103.200 Existing Km 103.200 to design Km 116.700 Existing Km 118.470 on AP/KNT Border to Sira Section of NH-544E in the State of Karnatakaon EPC mode under Annual plan 2022-23 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹167 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹167 Cr has not been significantly revised. Expenditure: ₹85 Cr (51.2% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to 2 Lane with Paved Shoulders from design Km 103.2 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618147. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2 Lane with Paved Shoulders from design Km 103.2 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.