Roads & HighwaysIPM · Central Project#618338

Widening to 2-Lane with Paved shoulder of Imphal to Jiribam section of NH-37 from Design Chainage 15.940 km to 33.120 Km Existing Chainage Km 15.946 to Km 33.395 Total length17.180 Km in the State of Manipur on EPC mode PKG-2 - Balance Works & Rectification works

Ministry of Road Transport & HighwaysManipur
Revised Cost: ₹195 CrUtilization: 83.5%

Original Cost

₹195 Cr

Baseline estimate

On budget

Revised Cost

₹195 Cr

Latest approved cost

Expenditure

₹163 Cr

Spent to date

Utilization

83.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹32 Cr

Budget left

Budget Utilization

83.5%
0%25%50%75%100%

Spent

₹163 Cr

Remaining

₹32 Cr

Total

₹195 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

18/03/2026

Revised Completion

31/10/2026

Completed

Project Details

Project Code618338
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateManipur
Data Month2026-08

Financial Summary

Original Cost₹195 Cr
Revised Cost₹195 Cr
Expenditure₹163 Cr
Original End Date18/03/2026
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹195 Cr — no cost escalation recorded.

Expenditure stands at ₹163 Cr, which is 83.5% of the revised project cost.

Remaining budget: ₹32 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening to 2-Lane with Paved shoulder of Imphal to Jiribam section of NH-37 from Design Chainage 15.940 km to 33.120 Km Existing Chainage Km 15.946 to Km 33.395 Total length17.180 Km in the State of Manipur on EPC mode PKG-2 - Balance Works & Rectification works is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹195.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening to 2-Lane with Paved shoulder of Imphal to Jiribam section of NH-37 fro"?
Widening to 2-Lane with Paved shoulder of Imphal to Jiribam section of NH-37 from Design Chainage 15.940 km to 33.120 Km Existing Chainage Km 15.946 to Km 33.395 Total length17.180 Km in the State of Manipur on EPC mode PKG-2 - Balance Works & Rectification works is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Manipur. Original cost: ₹195 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹195 Cr has not been significantly revised. Expenditure: ₹163 Cr (83.5% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening to 2-Lane with Paved shoulder of Imphal to Jiribam is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618338. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2-Lane with Paved shoulder of Imphal to Jiribam is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.