Widening to 2-Lane with Paved shoulder of Imphal to Jiribam section of NH-37 from Design Chainage 15.940 km to 33.120 Km Existing Chainage Km 15.946 to Km 33.395 Total length17.180 Km in the State of Manipur on EPC mode PKG-2 - Balance Works & Rectification works
Original Cost
₹195 Cr
Baseline estimate
Revised Cost
₹195 Cr
Latest approved cost
Expenditure
₹163 Cr
Spent to date
Utilization
83.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹32 Cr
Budget left
Budget Utilization
83.5%Spent
₹163 Cr
Remaining
₹32 Cr
Total
₹195 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
18/03/2026
Revised Completion
31/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹195 Cr — no cost escalation recorded.
Expenditure stands at ₹163 Cr, which is 83.5% of the revised project cost.
Remaining budget: ₹32 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to 2-Lane with Paved shoulder of Imphal to Jiribam section of NH-37 from Design Chainage 15.940 km to 33.120 Km Existing Chainage Km 15.946 to Km 33.395 Total length17.180 Km in the State of Manipur on EPC mode PKG-2 - Balance Works & Rectification works is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹195.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to 2-Lane with Paved shoulder of Imphal to Jiribam section of NH-37 fro"?
- Widening to 2-Lane with Paved shoulder of Imphal to Jiribam section of NH-37 from Design Chainage 15.940 km to 33.120 Km Existing Chainage Km 15.946 to Km 33.395 Total length17.180 Km in the State of Manipur on EPC mode PKG-2 - Balance Works & Rectification works is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Manipur. Original cost: ₹195 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹195 Cr has not been significantly revised. Expenditure: ₹163 Cr (83.5% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to 2-Lane with Paved shoulder of Imphal to Jiribam is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618338. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2-Lane with Paved shoulder of Imphal to Jiribam is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.