Original Cost
₹467 Cr
Baseline estimate
Revised Cost
₹467 Cr
Latest approved cost
Expenditure
₹571 Cr
Spent to date
Utilization
122.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Spent
₹571 Cr
Remaining
₹0 Cr
Total
₹467 Cr
Project Approved
Construction / Implementation
Original End Date
19/03/2023
Revised Completion
02/03/2026
Completed
Project is within original budget of ₹467 Cr — no cost escalation recorded.
Expenditure stands at ₹571 Cr, which is 122.3% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.