Roads & HighwaysIPM · Central Project#618030

Widening to 2 lane with paved shoulder from Km. 103.225 Pattadakal to Km. 133.00 Shirur cross of NH-367 in the state of Karnataka on EPC Mode.Job No. NH-367-KNT-2021-22-934

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹264 CrUtilization: 1.4%

Original Cost

₹264 Cr

Baseline estimate

On budget

Revised Cost

₹264 Cr

Latest approved cost

Expenditure

₹4 Cr

Spent to date

Utilization

1.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹260 Cr

Budget left

Budget Utilization

1.4%
0%25%50%75%100%

Spent

₹4 Cr

Remaining

₹260 Cr

Total

₹264 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/05/2024

Revised Completion

31/12/2026

Completed

Project Details

Project Code618030
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-06

Financial Summary

Original Cost₹264 Cr
Revised Cost₹264 Cr
Expenditure₹4 Cr
Original End Date27/05/2024
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹264 Cr — no cost escalation recorded.

Expenditure stands at ₹4 Cr, which is 1.4% of the revised project cost.

Remaining budget: ₹260 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening to 2 lane with paved shoulder from Km. 103.225 Pattadakal to Km. 133.00 Shirur cross of NH-367 in the state of Karnataka on EPC Mode.Job No. NH-367-KNT-2021-22-934 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹264.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening to 2 lane with paved shoulder from Km. 103.225 Pattadakal to Km. 133.00"?
Widening to 2 lane with paved shoulder from Km. 103.225 Pattadakal to Km. 133.00 Shirur cross of NH-367 in the state of Karnataka on EPC Mode.Job No. NH-367-KNT-2021-22-934 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹264 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹264 Cr has not been significantly revised. Expenditure: ₹4 Cr (1.4% of cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Widening to 2 lane with paved shoulder from Km. 103.225 Patt is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618030. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2 lane with paved shoulder from Km. 103.225 Patt is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.