Widening to 2-lane with paved shoulder from km 0.00 to 44.00 Kuru-Ghaghra section of NH-143A including re-construction of culverts and bridges.
Original Cost
₹153 Cr
Baseline estimate
Revised Cost
₹134 Cr
Latest approved cost
Expenditure
₹108 Cr
Spent to date
Utilization
80.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹26 Cr
Budget left
Budget Utilization
80.8%Spent
₹108 Cr
Remaining
₹26 Cr
Total
₹134 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
08/08/2023
Revised Completion
31/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹153 Cr — no cost escalation recorded.
Expenditure stands at ₹108 Cr, which is 80.8% of the revised project cost.
Remaining budget: ₹26 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to 2-lane with paved shoulder from km 0.00 to 44.00 Kuru-Ghaghra section of NH-143A including re-construction of culverts and bridges. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹153.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to 2-lane with paved shoulder from km 0.00 to 44.00 Kuru-Ghaghra sectio"?
- Widening to 2-lane with paved shoulder from km 0.00 to 44.00 Kuru-Ghaghra section of NH-143A including re-construction of culverts and bridges. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹153 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹153 Cr and has been revised to ₹134 Cr — a cost overrun of -12.6%. Expenditure to date: ₹108 Cr (80.8% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to 2-lane with paved shoulder from km 0.00 to 44.00 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618084. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2-lane with paved shoulder from km 0.00 to 44.00 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.