Roads & HighwaysIPM · Central Project#618345

Widening to 2-lane with Hard shoulder of Churachandpur to Tuivai Section from Km 48.587 to Km 69.875 in the State of Manipur on EPC mode under NHO Package-2B

Ministry of Road Transport & HighwaysManipur
Revised Cost: ₹366 CrUtilization: 54.3%

Original Cost

₹366 Cr

Baseline estimate

On budget

Revised Cost

₹366 Cr

Latest approved cost

Expenditure

₹199 Cr

Spent to date

Utilization

54.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹167 Cr

Budget left

Budget Utilization

54.3%
0%25%50%75%100%

Spent

₹199 Cr

Remaining

₹167 Cr

Total

₹366 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

04/08/2022

Revised Completion

31/10/2026

Completed

Project Details

Project Code618345
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateManipur
Data Month2026-08

Financial Summary

Original Cost₹366 Cr
Revised Cost₹366 Cr
Expenditure₹199 Cr
Original End Date04/08/2022
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹366 Cr — no cost escalation recorded.

Expenditure stands at ₹199 Cr, which is 54.3% of the revised project cost.

Remaining budget: ₹167 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening to 2-lane with Hard shoulder of Churachandpur to Tuivai Section from Km 48.587 to Km 69.875 in the State of Manipur on EPC mode under NHO Package-2B is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹366.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening to 2-lane with Hard shoulder of Churachandpur to Tuivai Section from Km"?
Widening to 2-lane with Hard shoulder of Churachandpur to Tuivai Section from Km 48.587 to Km 69.875 in the State of Manipur on EPC mode under NHO Package-2B is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Manipur. Original cost: ₹366 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹366 Cr has not been significantly revised. Expenditure: ₹199 Cr (54.3% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening to 2-lane with Hard shoulder of Churachandpur to Tu is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618345. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2-lane with Hard shoulder of Churachandpur to Tu is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.