Roads & HighwaysIPM · Central Project#618364

Widening to 2 Lane with Hard shoulder of Akegwo-Avangkhu section of NH-202K for Package-I Design Chainage 0000 Km to 34795 Km, in the State of Nagaland on EPC mode under NH O-NE

Ministry of Road Transport & HighwaysNagaland
Revised Cost: ₹430 CrUtilization: 0.0%

Original Cost

₹430 Cr

Baseline estimate

On budget

Revised Cost

₹430 Cr

Latest approved cost

Expenditure

₹0 Cr

Spent to date

Utilization

0.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹430 Cr

Budget left

Budget Utilization

0.0%
0%25%50%75%100%

Spent

₹0 Cr

Remaining

₹430 Cr

Total

₹430 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

23/02/2026

Revised Completion

23/02/2026

Completed

Project Details

Project Code618364
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateNagaland
Data Month2026-08

Financial Summary

Original Cost₹430 Cr
Revised Cost₹430 Cr
Expenditure₹0 Cr
Original End Date23/02/2026
Revised Date23/02/2026

Project Intelligence

Project is within original budget of ₹430 Cr — no cost escalation recorded.

Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.

Remaining budget: ₹430 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening to 2 Lane with Hard shoulder of Akegwo-Avangkhu section of NH-202K for Package-I Design Chainage 0000 Km to 34795 Km, in the State of Nagaland on EPC mode under NH O-NE is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹430.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening to 2 Lane with Hard shoulder of Akegwo-Avangkhu section of NH-202K for "?
Widening to 2 Lane with Hard shoulder of Akegwo-Avangkhu section of NH-202K for Package-I Design Chainage 0000 Km to 34795 Km, in the State of Nagaland on EPC mode under NH O-NE is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Nagaland. Original cost: ₹430 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹430 Cr has not been significantly revised. Expenditure: ₹0 Cr (N/A% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening to 2 Lane with Hard shoulder of Akegwo-Avangkhu sec is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618364. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2 Lane with Hard shoulder of Akegwo-Avangkhu sec is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.