Widening to 2-lane with Hard Shoulder configuration of Mana Ch. 0.00 to Mana Pass Ch. 50.987 road on NH-07 under Bharatmala Pariyojna in the state of Uttarakhand under Annual Plan 2022-23 length 50.987
Original Cost
₹574 Cr
Baseline estimate
Revised Cost
₹574 Cr
Latest approved cost
Expenditure
₹78 Cr
Spent to date
Utilization
13.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹496 Cr
Budget left
Budget Utilization
13.6%Spent
₹78 Cr
Remaining
₹496 Cr
Total
₹574 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
03/10/2027
Revised Completion
03/10/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹574 Cr — no cost escalation recorded.
Expenditure stands at ₹78 Cr, which is 13.6% of the revised project cost.
Remaining budget: ₹496 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening to 2-lane with Hard Shoulder configuration of Mana Ch. 0.00 to Mana Pass Ch. 50.987 road on NH-07 under Bharatmala Pariyojna in the state of Uttarakhand under Annual Plan 2022-23 length 50.987 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹574.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening to 2-lane with Hard Shoulder configuration of Mana Ch. 0.00 to Mana Pas"?
- Widening to 2-lane with Hard Shoulder configuration of Mana Ch. 0.00 to Mana Pass Ch. 50.987 road on NH-07 under Bharatmala Pariyojna in the state of Uttarakhand under Annual Plan 2022-23 length 50.987 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹574 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹574 Cr has not been significantly revised. Expenditure: ₹78 Cr (13.6% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening to 2-lane with Hard Shoulder configuration of Mana is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618207. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening to 2-lane with Hard Shoulder configuration of Mana is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.