Original Cost
₹187 Cr
Baseline estimate
Revised Cost
₹187 Cr
Latest approved cost
Expenditure
₹43 Cr
Spent to date
Utilization
23.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹144 Cr
Budget left
Spent
₹43 Cr
Remaining
₹144 Cr
Total
₹187 Cr
Project Approved
Construction / Implementation
Original End Date
04/02/2026
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹187 Cr — no cost escalation recorded.
Expenditure stands at ₹43 Cr, which is 23.0% of the revised project cost.
Remaining budget: ₹144 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.