Original Cost
₹206 Cr
Baseline estimate
Revised Cost
₹206 Cr
Latest approved cost
Expenditure
₹153 Cr
Spent to date
Utilization
74.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹53 Cr
Budget left
Spent
₹153 Cr
Remaining
₹53 Cr
Total
₹206 Cr
Project Approved
Construction / Implementation
Original End Date
03/06/2020
Revised Completion
Completed
Project is within original budget of ₹206 Cr — no cost escalation recorded.
Expenditure stands at ₹153 Cr, which is 74.2% of the revised project cost.
Remaining budget: ₹53 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.