Widening & Strenghteningof section from Bharthana chowk to Kodarkoot km.0.00 to km.40.00 of NH-91-A on EPC mode
Original Cost
₹262 Cr
Baseline estimate
Revised Cost
₹344 Cr
Latest approved cost
Expenditure
₹115 Cr
Spent to date
Utilization
33.6%
Of revised budget
Cost Status
+31.2%
+₹82 Cr increase
Remaining
₹228 Cr
Budget left
Budget Utilization
33.6%Spent
₹115 Cr
Remaining
₹228 Cr
Total
₹344 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹262 Cr
Revised Cost
₹344 Cr
Increase
+₹82 Cr
Escalation
+31.2%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
18/09/2024
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹82 Cr (31.2%) from the original estimate of ₹262 Cr.
Expenditure stands at ₹115 Cr, which is 33.6% of the revised project cost.
Remaining budget: ₹228 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening & Strenghteningof section from Bharthana chowk to Kodarkoot km.0.00 to km.40.00 of NH-91-A on EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹262.00 Cr, later revised to ₹343.77 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening & Strenghteningof section from Bharthana chowk to Kodarkoot km.0.00 to "?
- Widening & Strenghteningof section from Bharthana chowk to Kodarkoot km.0.00 to km.40.00 of NH-91-A on EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹262 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹262 Cr and has been revised to ₹344 Cr — a cost overrun of +31.2%. Expenditure to date: ₹115 Cr (33.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening & Strenghteningof section from Bharthana chowk to K is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618063. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening & Strenghteningof section from Bharthana chowk to K is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.