Original Cost
₹262 Cr
Baseline estimate
Revised Cost
₹344 Cr
Latest approved cost
Expenditure
₹112 Cr
Spent to date
Utilization
32.7%
Of revised budget
Cost Status
+31.2%
+₹82 Cr increase
Remaining
₹231 Cr
Budget left
Spent
₹112 Cr
Remaining
₹231 Cr
Total
₹344 Cr
Original Cost
₹262 Cr
Revised Cost
₹344 Cr
Increase
+₹82 Cr
Escalation
+31.2%
Project Approved
Construction / Implementation
Original End Date
18/09/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹82 Cr (31.2%) from the original estimate of ₹262 Cr.
Expenditure stands at ₹112 Cr, which is 32.7% of the revised project cost.
Remaining budget: ₹231 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.