Roads & HighwaysIPM · Central Project#617997

Widening of existing 2 lane to 4 lane with paved shoulder from Designed km 25.15 to km 56.70 Except Km 52.70 to 53.50 of NH-169 Nellisara Camp to Thirthahalli of NH-169 on Shimoga-Mangalore section in the state of Karnataka on EPC mode under Annual plan 2022-23 NH-169-KNT-2022-23-978 dated 08.03.2023

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹539 CrUtilization: 16.8%

Original Cost

₹539 Cr

Baseline estimate

On budget

Revised Cost

₹539 Cr

Latest approved cost

Expenditure

₹90 Cr

Spent to date

Utilization

16.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹449 Cr

Budget left

Budget Utilization

16.8%
0%25%50%75%100%

Spent

₹90 Cr

Remaining

₹449 Cr

Total

₹539 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

24/02/2028

Revised Completion

24/02/2028

Completed

Project Details

Project Code617997
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹539 Cr
Revised Cost₹539 Cr
Expenditure₹90 Cr
Original End Date24/02/2028
Revised Date24/02/2028

Project Intelligence

Project is within original budget of ₹539 Cr — no cost escalation recorded.

Expenditure stands at ₹90 Cr, which is 16.8% of the revised project cost.

Remaining budget: ₹449 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening of existing 2 lane to 4 lane with paved shoulder from Designed km 25.15 to km 56.70 Except Km 52.70 to 53.50 of NH-169 Nellisara Camp to Thirthahalli of NH-169 on Shimoga-Mangalore section in the state of Karnataka on EPC mode under Annual plan 2022-23 NH-169-KNT-2022-23-978 dated 08.03.2023 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹539.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening of existing 2 lane to 4 lane with paved shoulder from Designed km 25.15"?
Widening of existing 2 lane to 4 lane with paved shoulder from Designed km 25.15 to km 56.70 Except Km 52.70 to 53.50 of NH-169 Nellisara Camp to Thirthahalli of NH-169 on Shimoga-Mangalore section in the state of Karnataka on EPC mode under Annual plan 2022-23 NH-169-KNT-2022-23-978 dated 08.03.2023 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹539 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹539 Cr has not been significantly revised. Expenditure: ₹90 Cr (16.8% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening of existing 2 lane to 4 lane with paved shoulder fr is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617997. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening of existing 2 lane to 4 lane with paved shoulder fr is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.