Widening and Up-gradation to 2-Lane with Paved Shoulder of configuration and geometric improvement from Km 0.000 to Km 16.990 on Chenani Sudhmahadev section of NH-244 in UT of Jammu and Kashmir to be executed on EPC basis
Original Cost
₹256 Cr
Baseline estimate
Revised Cost
₹256 Cr
Latest approved cost
Expenditure
₹241 Cr
Spent to date
Utilization
94.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹15 Cr
Budget left
Budget Utilization
94.0%Spent
₹241 Cr
Remaining
₹15 Cr
Total
₹256 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
21/11/2020
Revised Completion
15/12/2025
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹256 Cr — no cost escalation recorded.
Expenditure stands at ₹241 Cr, which is 94.0% of the revised project cost.
Remaining budget: ₹15 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening and Up-gradation to 2-Lane with Paved Shoulder of configuration and geometric improvement from Km 0.000 to Km 16.990 on Chenani Sudhmahadev section of NH-244 in UT of Jammu and Kashmir to be executed on EPC basis is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹256.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening and Up-gradation to 2-Lane with Paved Shoulder of configuration and geo"?
- Widening and Up-gradation to 2-Lane with Paved Shoulder of configuration and geometric improvement from Km 0.000 to Km 16.990 on Chenani Sudhmahadev section of NH-244 in UT of Jammu and Kashmir to be executed on EPC basis is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹256 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹256 Cr has not been significantly revised. Expenditure: ₹241 Cr (94.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening and Up-gradation to 2-Lane with Paved Shoulder of c is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618397. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and Up-gradation to 2-Lane with Paved Shoulder of c is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.