Roads & HighwaysIPM · Central Project#618222

Widening and Strengthening up gradation to 2 lane with paved shoulder from existing chainage Km 192.98 to Km 229.820 design chainage Km 162.800 to Km 198.18 under 31 BRTF on Akhnoor-Poonch Road NH-144A in the UT of Jammu and Kashmir under Project Sampark Border Roads Organisation BRO on EPC Mode Package-VIII Job No NH-144A-J&K-2022-2023-111

Ministry of Road Transport & HighwaysJammu & Kashmir
Revised Cost: ₹562 CrUtilization: 28.2%

Original Cost

₹562 Cr

Baseline estimate

On budget

Revised Cost

₹562 Cr

Latest approved cost

Expenditure

₹159 Cr

Spent to date

Utilization

28.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹403 Cr

Budget left

Budget Utilization

28.2%
0%25%50%75%100%

Spent

₹159 Cr

Remaining

₹403 Cr

Total

₹562 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

04/01/2026

Revised Completion

31/03/2027

Completed

Project Details

Project Code618222
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹562 Cr
Revised Cost₹562 Cr
Expenditure₹159 Cr
Original End Date04/01/2026
Revised Date31/03/2027

Project Intelligence

Project is within original budget of ₹562 Cr — no cost escalation recorded.

Expenditure stands at ₹159 Cr, which is 28.2% of the revised project cost.

Remaining budget: ₹403 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening and Strengthening up gradation to 2 lane with paved shoulder from existing chainage Km 192.98 to Km 229.820 design chainage Km 162.800 to Km 198.18 under 31 BRTF on Akhnoor-Poonch Road NH-144A in the UT of Jammu and Kashmir under Project Sampark Border Roads Organisation BRO on EPC Mode Package-VIII Job No NH-144A-J&K-2022-2023-111 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹562.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening and Strengthening up gradation to 2 lane with paved shoulder from exist"?
Widening and Strengthening up gradation to 2 lane with paved shoulder from existing chainage Km 192.98 to Km 229.820 design chainage Km 162.800 to Km 198.18 under 31 BRTF on Akhnoor-Poonch Road NH-144A in the UT of Jammu and Kashmir under Project Sampark Border Roads Organisation BRO on EPC Mode Package-VIII Job No NH-144A-J&K-2022-2023-111 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹562 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹562 Cr has not been significantly revised. Expenditure: ₹159 Cr (28.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening and Strengthening up gradation to 2 lane with paved is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618222. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and Strengthening up gradation to 2 lane with paved is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.