Original Cost
₹562 Cr
Baseline estimate
Revised Cost
₹562 Cr
Latest approved cost
Expenditure
₹137 Cr
Spent to date
Utilization
24.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹425 Cr
Budget left
Spent
₹137 Cr
Remaining
₹425 Cr
Total
₹562 Cr
Project Approved
Construction / Implementation
Original End Date
04/01/2026
Revised Completion
30/12/2026
Completed
Project is within original budget of ₹562 Cr — no cost escalation recorded.
Expenditure stands at ₹137 Cr, which is 24.4% of the revised project cost.
Remaining budget: ₹425 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.