Roads & HighwaysIPM · Central Project#617921

Widening and strengthening to 2LPS including LA of Kandarpur-Balikuda from km 277/500 to 318/970 of NH-55 in the State of Odisha under Annual Plan 2021-22.

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹500 CrUtilization: 70.5%

Original Cost

₹500 Cr

Baseline estimate

On budget

Revised Cost

₹500 Cr

Latest approved cost

Expenditure

₹353 Cr

Spent to date

Utilization

70.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹147 Cr

Budget left

Budget Utilization

70.5%
0%25%50%75%100%

Spent

₹353 Cr

Remaining

₹147 Cr

Total

₹500 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

04/06/2025

Revised Completion

30/06/2027

Completed

Project Details

Project Code617921
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹500 Cr
Revised Cost₹500 Cr
Expenditure₹353 Cr
Original End Date04/06/2025
Revised Date30/06/2027

Project Intelligence

Project is within original budget of ₹500 Cr — no cost escalation recorded.

Expenditure stands at ₹353 Cr, which is 70.5% of the revised project cost.

Remaining budget: ₹147 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening and strengthening to 2LPS including LA of Kandarpur-Balikuda from km 277/500 to 318/970 of NH-55 in the State of Odisha under Annual Plan 2021-22. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹500.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening and strengthening to 2LPS including LA of Kandarpur-Balikuda from km 27"?
Widening and strengthening to 2LPS including LA of Kandarpur-Balikuda from km 277/500 to 318/970 of NH-55 in the State of Odisha under Annual Plan 2021-22. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹500 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹500 Cr has not been significantly revised. Expenditure: ₹353 Cr (70.5% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening and strengthening to 2LPS including LA of Kandarpur is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617921. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and strengthening to 2LPS including LA of Kandarpur is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.